Fluidstack AI supercomputer, France
Fluidstack · France · 1 GW · Announced
Fluidstack signed an MoU with the French government for a nuclear-powered AI supercomputer of up to 1 GW, with a EUR 10 billion first phase.
Facts
As of Feb 10, 2025- Capacity
- 1 GWUp to 1 GW of dedicated AI compute, expandable beyond 1 GW by 2028
- Chips
- About 500,000 next-generation AI chips in phase 1
- Power
- French grid, predominantly nuclear
- Announced
- Feb 10, 2025
- Target online
- 2026
Related builds
AnnouncedTarget 20313.1 GW
SoftBank AI data center campus, Hauts-de-France (Dunkirk, Bosquel, Bouchain)SoftBank plans an initial EUR 45 billion for 3.1 GW of AI data centers in Dunkirk, Bosquel and Bouchain by 2031.Announced1.4 GW
MGX, Bpifrance, Mistral AI and Nvidia AI campus, Paris regionA joint venture of MGX, Bpifrance, Mistral AI and Nvidia plans Europe's largest AI campus in the Paris region, scaling to 1.4 GW.Announced1 GW
Brookfield AI data center, CambraiBrookfield's EUR 20 billion French data center program is anchored by a mega-project in Cambrai.Announced700 MW
Data4 Escaudain campusData4 launched a EUR 5 billion, 700 MW campus at the former Parc des Soufflantes site in Escaudain, northern France.Partly onlineTarget 2027200 MW
Mistral AI compute sites, EssonneMistral AI runs a 40 MW training site at Bruyeres-le-Chatel and is adding sites in Essonne within a EUR 4 billion compute program.BuildingTarget H2 2026168 MW
Abernathy AI campusA Fluidstack and TeraWulf joint venture building 168 MW of AI capacity at Abernathy, Texas; TeraWulf agreed in July 2026 to sell its stake to Fluidstack. | Build | Location | Capacity | Status | Target online |
|---|
SoftBank AI data center campus, Hauts-de-France (Dunkirk, Bosquel, Bouchain)SoftBank plans an initial EUR 45 billion for 3.1 GW of AI data centers in Dunkirk, Bosquel and Bouchain by 2031.SoftBank Group · Dunkirk, France · Announced · Target 2031 | Dunkirk, France | 3.1 GW | Announced | 2031 |
MGX, Bpifrance, Mistral AI and Nvidia AI campus, Paris regionA joint venture of MGX, Bpifrance, Mistral AI and Nvidia plans Europe's largest AI campus in the Paris region, scaling to 1.4 GW.MGX · France · Announced | France | 1.4 GW | Announced | |
Brookfield AI data center, CambraiBrookfield's EUR 20 billion French data center program is anchored by a mega-project in Cambrai.Brookfield Asset Management · Cambrai, France · Announced | Cambrai, France | 1 GW | Announced | |
Data4 Escaudain campusData4 launched a EUR 5 billion, 700 MW campus at the former Parc des Soufflantes site in Escaudain, northern France.Data4 · Escaudain, France · Announced | Escaudain, France | 700 MW | Announced | |
Mistral AI compute sites, EssonneMistral AI runs a 40 MW training site at Bruyeres-le-Chatel and is adding sites in Essonne within a EUR 4 billion compute program.Mistral AI · Bruyeres-le-Chatel, France · Partly online · Target 2027 | Bruyeres-le-Chatel, France | 200 MW | Partly online | 2027 |
Abernathy AI campusA Fluidstack and TeraWulf joint venture building 168 MW of AI capacity at Abernathy, Texas; TeraWulf agreed in July 2026 to sell its stake to Fluidstack.Fluidstack · Abernathy, Texas · Building · Target H2 2026 | Abernathy, Texas | 168 MW | Building | H2 2026 |
Sources and links