Biggest builds
by planned megawatts1
Project MatadorFermi America is building a private power and AI data center campus in Carson County near Amarillo, Texas, planned at 11 GW or more.Building11 GW2
HyperionMeta's largest campus, phased through 2030; in July 2026 the plan grew to 5 GW and up to $50 billion.Building5 GW3Nanto Campus, ToyamaNanto City and GigaStream Toyama plan a 3.1 GW data center hub, with a 400 MW first phase set for late 2028.Announced · Unverified3.1 GW4
SoftBank AI data center campus, Hauts-de-France (Dunkirk, Bosquel, Bouchain)SoftBank plans an initial EUR 45 billion for 3.1 GW of AI data centers in Dunkirk, Bosquel and Bouchain by 2031.Announced3.1 GW5
AirTrunk data center, Raigad (Pen Growth Centre)Maharashtra gave AirTrunk a letter of intent for land at the Raigad Pen Growth Centre for a 3 GW, INR 2 lakh crore data center project.Announced3 GW6
AWS Northern Indiana campusesAmazon plans $15 billion for new data center campuses in Northern Indiana adding 2.4 GW, on top of its St. Joseph County project.Announced2.4 GW7
Caldwell Valley Technology ParkTract assembled a nearly 3,000 acre campus in Caldwell County, Texas, planned for over 2 GW of data centers from 2028.Announced · Unverified2 GW8
Envision Galaxy Campus, UlanqabEnvision commissioned its 2 GW Galaxy AI campus in Ulanqab, Inner Mongolia, powered directly by renewable energy.Partly online2 GW9
Sweetwater 1 and 2IREN 2 GW grid-connected site at Sweetwater, Texas; the first substation was energized in 2026 and initial AI capacity is planned for 2027.Building2 GW10
Crusoe Wyoming (Project Jade)A 1.8 GW campus planned with Tallgrass in southeast Wyoming, paused indefinitely in June 2026 at an unnamed customer's request.Paused1.8 GW11Fortune Data Center Park, near HyderabadFortune Hospitality & Infra plans a 1.6 GW hyperscale data center park on 200 acres next to Bharat Future City near Hyderabad.Announced1.6 GW12
Rio AI City, JacarepaguaElea plans Rio AI City near Rio's Olympic Park, a 10-building campus of 1.5 GW scalable to 3.5 GW.Announced1.5 GW13
YTL Power and JLand campus, JohorYTL Power and JLand plan a gigawatt-scale data center campus in Johor, estimated at 1.3 GW to 1.5 GW.Announced1.5 GW14Western Downs Digital Park (Anthropic)Anthropic will lease part of Zerra DC's planned 1.44 GW Western Downs Digital Park near Dalby, Queensland, for inference.Announced1.4 GW15
CDC Gregadoo campus, Wagga WaggaCDC is seeking approval for a 1.4 GW sovereign compute campus at Gregadoo near Wagga Wagga, pitched at about AUD 15 billion.Announced1.4 GW16
MGX, Bpifrance, Mistral AI and Nvidia AI campus, Paris regionA joint venture of MGX, Bpifrance, Mistral AI and Nvidia plans Europe's largest AI campus in the Paris region, scaling to 1.4 GW.Announced1.4 GW17
Vantage Frontier campusTen buildings on 1,200 acres, 1.4 GW of GPU capacity, first building due in the second half of 2026. OpenAI named Shackelford County for an Oracle-developed Stargate site a month later.Building1.4 GW18
Monarch Compute CampusNscale bought the Monarch campus in Mason County, West Virginia, and signed a letter of intent to host up to 1.35 GW of Vera Rubin GPUs for Microsoft.Announced · Unverified1.4 GW19
Bell AI Fabric hub, SaskatchewanBell signed a non-binding MoU with Saskatchewan to add up to 900 MW of Bell AI Fabric capacity toward a 1.2 GW AI hub.Announced1.2 GW20
Nebius Independence AI factoryNebius broke ground in May 2026 on an owned AI factory in Independence, Missouri, planned for up to 1.2 GW.Building1.2 GW21
Nebius Pennsylvania AI factoryNebius announced a second owned US gigawatt-scale site in Pennsylvania, with power secured for up to 1.2 GW, delivered in phases from 2027.Announced1.2 GW22
SINES Data Campus (Start Campus)Start Campus is building a 1.2 GW campus at a former coal plant in Sines, where Nscale deploys over 66,000 Nvidia Rubin GPUs for Microsoft.Partly online1.2 GW23
Stargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.Partly online1.2 GW24
Stargate Milam County (Freebird)SB Energy builds and runs the 1.2 GW site; phase one, four data halls in 548,950 sq ft, is filed for completion on October 15, 2026.Building1.2 GW25
Brookfield AI data center, CambraiBrookfield's EUR 20 billion French data center program is anchored by a mega-project in Cambrai.Announced1 GW26
Crusoe Childress campusCrusoe and Lancium plan a 1 GW AI data center campus in Childress, Texas, for an unnamed hyperscaler, repeating their Abilene model.Announced1 GW27
Data Center Valley, EkibastuzThe USD 10 billion Data Center Valley in Ekibastuz, Kazakhstan, backed by Nvidia and Firebird, is planned to scale to 1 GW.Building1 GW28
Digital Connexion 1 GW campus, VisakhapatnamDigital Connexion, the Reliance, Brookfield and Digital Realty JV, plans a USD 11 billion, 1 GW campus on 400 acres near Visakhapatnam.Announced1 GW29
EdgeConneX campus, SkellefteaEdgeConneX plans to buy a Lyten site in Skelleftea, Sweden, that could become a campus of up to 1 GW.Announced1 GW30
Elsham Tech Park, North LincolnshireElsham Tech Park, a 1 GW AI data center campus on the former RAF Elsham Wolds airfield, received outline planning approval in March 2026.Announced1 GW31
Fluidstack AI supercomputer, FranceFluidstack signed an MoU with the French government for a nuclear-powered AI supercomputer of up to 1 GW, with a EUR 10 billion first phase.Announced1 GW32
Google AI hub VisakhapatnamA $15 billion, 1 GW AI hub with AdaniConneX and Airtel; the first phase is expected by mid-2028.Announced1 GW33
Meta El PasoMeta's 29th data center, broken ground in October 2025 as a site that can scale to 1 GW.Building1 GW34
Meta Sturgeon County data centerMeta broke ground on a 1 GW AI-optimized data center in Sturgeon County, Alberta, its first in Canada, worth more than CAD 13 billion.Building1 GW35
Microsoft and G42 geothermal data center, OlkariaKenya suspended the USD 1 billion geothermal-powered data center planned with Microsoft and G42 at Olkaria over power needs.Paused1 GW36
Morris Technology ParkTract bought 343 acres in Morris, Illinois, for a 1 GW data center campus with ComEd power, first energization targeted for 2028.Announced · Unverified1 GW37
PrometheusMeta's first gigawatt AI supercluster, expected online in 2026.Building1 GW38Stafford Technology CampusSTACK plans its largest development, the 1 GW-plus Stafford Technology Campus in Stafford County, Virginia.Announced1 GW39
Stargate Michigan (The Barn)Three 550,000 sq ft buildings developed by Related Digital; funding closed in April 2026 and all buildings were under construction by June.Building1 GW40
Stargate UAEThe first 1 GW phase of the 5 GW UAE-US AI Campus, built by G42 with OpenAI, Oracle, Nvidia, Cisco and SoftBank. The UAE is now revising the campus into several sites.Building1 GW41
Stargate Wisconsin (Lighthouse)Four data centers with close to a gigawatt of AI capacity, developed by Vantage with Oracle for OpenAI; completion scheduled for 2028.Building1 GW42SuperX AI computing park proposal, KazakhstanSuperX is in talks with Kazakhstan's government on a proposed 1 GW AI computing park, phased from 2027 to 2029.Announced1 GW43
TCS HyperVault AI data center campus, HyderabadTCS subsidiary HyperVault secured 264 acres in Hyderabad for an AI data center campus of up to 1 GW, with up to INR 70,000 crore planned.Announced · Unverified1 GW44
Vantage South Wales campuses (Newport CWL1, Bridgend, Bro Tathan)Vantage plans more than 1 GW across Newport, Bridgend and Bro Tathan in the South Wales AI Growth Zone, with Nebius leasing capacity at CWL1.Partly online1 GW45
Zankore by Indosat AI factory platformIndosat, Ooredoo, Nokia and Nvidia launched Zankore, targeting 1 GW of Nvidia AI factory capacity in Indonesia.Announced1 GW46
Colossus 2Operational from September 3, 2026 at about 946 MW of IT power, by Epoch AI's count the largest AI data center.Online946 MW47
CloudHQ Queretaro campusCloudHQ plans a USD 4.8 billion, six-building campus in Queretaro with 900 MW planned and the first 200 MW of power secured.Announced900 MW48
Crusoe Abilene expansion for MicrosoftMicrosoft leases 900 MW at Crusoe's Abilene campus, the capacity OpenAI and Oracle chose not to take when they stopped at 1.2 GW.Announced900 MW49
HeliosGalaxy converted its Helios bitcoin site in Dickens County, Texas, into an AI campus leased to CoreWeave; 133 MW of IT was delivered in Q2 2026.Partly online800 MW50
CyrusOne Freestone CountyCyrusOne plans a data center beside the Freestone Energy Center in Freestone County, Texas, with 380 MW contracted and 380 MW more in Phase 2.Announced · Unverified760 MW51
Brookfield AI center, StrangnasBrookfield plans up to SEK 95 billion for a large AI center in Strangnas, Sweden, with capacity rising from 300 MW to 750 MW.Announced750 MW52
Beacon PointHut 8 1 GW campus in Nueces County, Texas, fully leased as 704 MW of IT capacity to one unnamed high-investment-grade tenant.Building704 MW53
Data4 Escaudain campusData4 launched a EUR 5 billion, 700 MW campus at the former Parc des Soufflantes site in Escaudain, northern France.Announced700 MW54
Jurong Island data centre parkSingapore set aside 20 hectares on Jurong Island for a green data center park of up to 700 MW.Announced700 MW55
Firmus Project Southgate, South Australia (Tailem Bend, Stirling North)Firmus secured 600 MW of firm power from Gunvor for its first South Australian AI factory campuses at Tailem Bend and Stirling North.Announced600 MW56
NEXTDC S7 AI campus with OpenAI, Eastern CreekNEXTDC plans a sovereign AI campus at its S7 site in Western Sydney with OpenAI as anchor tenant under OpenAI for Countries.Announced550 MW57
Prime Data Centers ESB01, EsbjergPrime Data Centers and Brunswick Real Estate plan a 550 MW campus on Nordre Tovrupvej in Esbjerg, with a USD 2.3 billion first phase.Announced550 MW58
Bell AI Fabric supercluster, British ColumbiaBell AI Fabric plans a hydro-powered AI data center supercluster in British Columbia of up to 500 MW across six facilities.Announced500 MW59Dakhla green data centerMorocco plans a 500 MW green data center in Dakhla powered by a dedicated solar and wind farm.Announced · Unverified500 MW60
Digital Edge CGK campus, BekasiDigital Edge topped out CGK1 at its USD 4.5 billion, 500 MW campus in Bekasi and signed a 1.45 GW power deal with PLN.Building500 MW
Every build, with filters →Where
202 builds on the map- Online
- Building
- Announced
- StoppedPaused or cancelled
By placeplanned megawatts
Texas27 builds27 GW
India13 builds9 GW
France6 builds7.4 GW
Louisiana3 builds5.2 GW
Australia7 builds5 GW
Japan5 builds3.9 GW
Indonesia10 builds3.2 GW
Canada5 builds2.9 GW
United Kingdom7 builds2.6 GW
Indiana3 builds2.4 GW
Malaysia7 builds2.2 GW
Sweden6 builds2.2 GW
China1 build2 GW
Kazakhstan2 builds2 GW
Wyoming1 build1.8 GW
Brazil4 builds1.8 GW
Saudi Arabia7 builds1.6 GW
West Virginia1 build1.4 GW
Virginia4 builds1.3 GW
United Arab Emirates3 builds1.3 GW
What changed
after the announcementChanges6
Newly tracked40