AI data center builds

220 builds · 93 gigawatts

Black Pearl

Cipher Digital · Wink, Texas · 300 MW · Building

Source

Cipher is converting its Black Pearl site in Wink, Texas, into a 300 MW AI data center leased to Amazon Web Services for 15 years.

Facts

As of Nov 3, 2025
Tenant
AWS
Capacity
300 MW300 MW gross, 216 MW critical IT under a 15-year AWS lease
Power
Oncor 138 kV interconnection, ERCOT
Location
Wink, Texas · Cloud regions nearby
Announced
Nov 3, 2025
Target online
Oct 2026Rent from Oct 2026 in phases
On file since
Nov 3, 2025 · SEC

Related builds

BuildingTarget 202611 GWProject MatadorFermi America is building a private power and AI data center campus in Carson County near Amarillo, Texas, planned at 11 GW or more.Fermi America · Amarillo, TexasAnnouncedTarget H1 2028Unverified2 GWCaldwell Valley Technology ParkTract assembled a nearly 3,000 acre campus in Caldwell County, Texas, planned for over 2 GW of data centers from 2028.Tract · Lockhart, TexasBuildingTarget 20272 GWSweetwater 1 and 2IREN 2 GW grid-connected site at Sweetwater, Texas; the first substation was energized in 2026 and initial AI capacity is planned for 2027.IREN · Sweetwater, TexasBuildingTarget H2 20261.4 GWVantage Frontier campusTen buildings on 1,200 acres, 1.4 GW of GPU capacity, first building due in the second half of 2026. OpenAI named Shackelford County for an Oracle-developed Stargate site a month later.Vantage Data Centers · Shackelford County, Texas · $25BPartly onlineTarget 20261.2 GWStargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.Oracle for OpenAI · Abilene, Texas · NVIDIA GB200 · 3 changesBuildingTarget Oct 15, 20261.2 GWStargate Milam County (Freebird)SB Energy builds and runs the 1.2 GW site; phase one, four data halls in 548,950 sq ft, is filed for completion on October 15, 2026.SB Energy for OpenAI · Milam County, Texas · 1 changeAnnouncedTarget Q3 20261 GWCrusoe Childress campusCrusoe and Lancium plan a 1 GW AI data center campus in Childress, Texas, for an unnamed hyperscaler, repeating their Abilene model.Crusoe · Childress, TexasBuilding1 GWMeta El PasoMeta's 29th data center, broken ground in October 2025 as a site that can scale to 1 GW.Meta · El Paso, Texas · $10B · 1 change