Crusoe Childress campus

Crusoe · Childress, Texas · 1 GW · Announced

Source

Crusoe and Lancium plan a 1 GW AI data center campus in Childress, Texas, for an unnamed hyperscaler, repeating their Abilene model.

Facts

As of Jul 15, 2026
Operator
Crusoe
Partners
Lancium
Capacity
1 GW1.0 GW grid-connected campus for an unnamed leading hyperscale technology company
Power
Grid-connected; Lancium manages energy infrastructure
Location
Childress, Texas · Cloud regions nearby
Announced
Jul 15, 2026
Target online
Q3 2026Construction to begin Q3 2026
On file since
Jul 15, 2026 · lancium.com

Related builds

BuildingTarget 202611 GWProject MatadorFermi America is building a private power and AI data center campus in Carson County near Amarillo, Texas, planned at 11 GW or more.Fermi America · Amarillo, TexasAnnouncedTarget H1 2028Unverified2 GWCaldwell Valley Technology ParkTract assembled a nearly 3,000 acre campus in Caldwell County, Texas, planned for over 2 GW of data centers from 2028.Tract · Lockhart, TexasBuildingTarget 20272 GWSweetwater 1 and 2IREN 2 GW grid-connected site at Sweetwater, Texas; the first substation was energized in 2026 and initial AI capacity is planned for 2027.IREN · Sweetwater, TexasPaused1.8 GWCrusoe Wyoming (Project Jade)A 1.8 GW campus planned with Tallgrass in southeast Wyoming, paused indefinitely in June 2026 at an unnamed customer's request.Crusoe · Cheyenne area, Wyoming · 1 changeBuildingTarget H2 20261.4 GWVantage Frontier campusTen buildings on 1,200 acres, 1.4 GW of GPU capacity, first building due in the second half of 2026. OpenAI named Shackelford County for an Oracle-developed Stargate site a month later.Vantage Data Centers · Shackelford County, Texas · $25BPartly onlineTarget 20261.2 GWStargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.Oracle for OpenAI · Abilene, Texas · NVIDIA GB200 · 3 changesBuildingTarget Oct 15, 20261.2 GWStargate Milam County (Freebird)SB Energy builds and runs the 1.2 GW site; phase one, four data halls in 548,950 sq ft, is filed for completion on October 15, 2026.SB Energy for OpenAI · Milam County, Texas · 1 changeBuilding1 GWMeta El PasoMeta's 29th data center, broken ground in October 2025 as a site that can scale to 1 GW.Meta · El Paso, Texas · $10B · 1 change