Crusoe
Runs 3 builds, partner on 1 build · 3.7 GW stated · 2 locations · Registry profile
Builds
| Build | Capacity | |||
|---|---|---|---|---|
| Cheyenne area, Wyoming | 1.8 GW | Paused1 change | ||
| Childress, Texas | 1 GW | Announced | Q3 2026 | |
| Abilene, Texas | 900 MW | Announced | ||
| Abilene, Texas | 1.2 GW | Partly online3 changes | 2026 |
What changed
Newest first| Date | Build | ||
|---|---|---|---|
| Jun 9, 2026 | Announced to PausedSource | Yahoo | |
| Mar 6, 2026 | Capacity 1.8 GW to 1.2 GWOracle and OpenAI dropped the expansion to 2 GWSource | DCD | |
| Sep 23, 2025 | Capacity 1.2 GW to 1.8 GWA potential 600 MW expansion near the siteSource | OpenAI | |
| Sep 23, 2025 | Building to Partly onlineSource | OpenAI |