Every build announced and every change since, dated as the source reports it. Append-only; JSON at /api/changes.

47 changes

DateBuild
Sep 24, 2026Project Jupiter (Stargate New Mexico)Oracle sent a force majeure notice over Project Jupiter; the gas pipeline rights-of-way were refused in March and July
Sep 22, 2026Nebius VinelandNJ DEP fined the developer more than $1 million for running 62 gas generators without a permit
Sep 18, 2026AWS Richmond CountyNC regulators denied Duke Energy's $584 million gas turbine proposal near the campus
Sep 10, 2026Stargate UAEThe UAE is revising the 5 GW campus into a network of sites after attacks linked to the US-Iran war; G42 says work is progressing
Sep 3, 2026Colossus 2Building to Online
Sep 3, 2026Colossus 2Announced
Aug 29, 2026AWS Richmond CountyState regulators approved the air permits for the diesel generators
Jul 13, 2026HyperionInvestment $10B to $50B
Jul 13, 2026HyperionCapacity 2 GW to 5 GW
Jul 6, 2026Justified Data campusAnnounced
Jun 23, 2026Fairwater WisconsinBuilding to Online
Jun 9, 2026Crusoe Wyoming (Project Jade)Announced to Paused
Jun 1, 2026Stargate Michigan (The Barn)Announced to Building
Apr 22, 2026Stargate Milam County (Freebird)Target online 2026 to Oct 15, 2026
Apr 15, 2026Nscale Narvik (was Stargate Norway)Tenant openai to microsoft
Apr 9, 2026Stargate UKAnnounced to Paused
Mar 27, 2026Crusoe Abilene expansion for MicrosoftAnnounced
Mar 6, 2026Stargate Wisconsin (Lighthouse)Announced to Building
Mar 6, 2026Stargate AbileneCapacity 1.8 GW to 1.2 GW
Nov 14, 2025Google Texas campusesAnnounced
Nov 12, 2025Fairwater AtlantaAnnounced
Oct 30, 2025Stargate Michigan (The Barn)Announced
Oct 22, 2025Stargate Wisconsin (Lighthouse)Announced
Oct 15, 2025Meta El PasoInvestment $1.5B to $10B
Oct 15, 2025Meta El PasoAnnounced
Oct 14, 2025Google AI hub VisakhapatnamAnnounced
Oct 10, 2025Stargate ArgentinaAnnounced
Sep 23, 2025Stargate Milam County (Freebird)Announced
Sep 23, 2025Stargate LordstownAnnounced
Sep 23, 2025Project Jupiter (Stargate New Mexico)Announced
Sep 23, 2025Stargate AbileneCapacity 1.2 GW to 1.8 GW
Sep 23, 2025Stargate AbileneBuilding to Partly online
Sep 18, 2025Fairwater WisconsinInvestment $3.3B to $7.3B
Sep 16, 2025Stargate UKAnnounced
Sep 8, 2025Nebius VinelandAnnounced
Aug 19, 2025Vantage Frontier campusAnnounced
Jul 31, 2025Nscale Narvik (was Stargate Norway)Announced
Jul 14, 2025PrometheusAnnounced
Jul 2025Crusoe Wyoming (Project Jade)Announced
Jun 9, 2025AWS Pennsylvania campusesAnnounced
Jun 4, 2025AWS Richmond CountyAnnounced
May 22, 2025Stargate UAEAnnounced
Jan 21, 2025Stargate AbileneAnnounced
Dec 4, 2024HyperionAnnounced
Dec 3, 2024Project RainierAnnounced
Sep 2, 2024ColossusAnnounced
May 2024Fairwater WisconsinAnnounced