WBS Power formed a JV to co-locate a 500 MW hyperscale data center with its Project Jupiter battery and solar site on a former German airfield.
Facts
As of Dec 1, 2025- Operator
- WBS Power
- Partners
- prime capital
- Capacity
- 500 MW500 MW hyperscale data center co-located with BESS and solar
- Power
- Shared 380 kV grid connection with 500 MW BESS and 150 MWp solar
- Location
- Germany · Cloud regions nearby
- Announced
- Dec 2025
- On file since
- Dec 1, 2025 · w.media
Related builds
| Build | Capacity | |||
|---|---|---|---|---|
| Lubbenau, Germany | 200 MW | Building | 2027 | |
| Munich, Germany | Not stated | Announced | Early 2026 | |
| Dietzenbach, Germany | Not stated | Announced | 2029 | |
| Bergheim, Germany | Not stated | Building |
Sources and links
- WBS power sells Project Jupiter, and forms JV for 500 MW data center · w.media · Dec 5, 2025
Across fru.dev: WBS Power on Companies, cloud regions on Regions.