AI data center builds

220 builds · 93 gigawatts

Every AI data center build, by megawatts

BuildingTarget 202611 GWProject MatadorFermi America is building a private power and AI data center campus in Carson County near Amarillo, Texas, planned at 11 GW or more.Fermi America · Amarillo, TexasBuildingTarget 20305 GWHyperionMeta's largest campus, phased through 2030; in July 2026 the plan grew to 5 GW and up to $50 billion.Meta · Richland Parish, Louisiana · $50B · 2 changesAnnouncedTarget 2028Unverified3.1 GWNanto Campus, ToyamaNanto City and GigaStream Toyama plan a 3.1 GW data center hub, with a 400 MW first phase set for late 2028.GigaStream Toyama · Nanto, JapanAnnouncedTarget 20313.1 GWSoftBank AI data center campus, Hauts-de-France (Dunkirk, Bosquel, Bouchain)SoftBank plans an initial EUR 45 billion for 3.1 GW of AI data centers in Dunkirk, Bosquel and Bouchain by 2031.SoftBank Group · Dunkirk, FranceAnnounced3 GWAirTrunk data center, Raigad (Pen Growth Centre)Maharashtra gave AirTrunk a letter of intent for land at the Raigad Pen Growth Centre for a 3 GW, INR 2 lakh crore data center project.AirTrunk · Pen, India · $21BAnnounced2.4 GWAWS Northern Indiana campusesAmazon plans $15 billion for new data center campuses in Northern Indiana adding 2.4 GW, on top of its St. Joseph County project.AWS · Indiana · $15BAnnouncedTarget H1 2028Unverified2 GWCaldwell Valley Technology ParkTract assembled a nearly 3,000 acre campus in Caldwell County, Texas, planned for over 2 GW of data centers from 2028.Tract · Lockhart, TexasPartly online2 GWEnvision Galaxy Campus, UlanqabEnvision commissioned its 2 GW Galaxy AI campus in Ulanqab, Inner Mongolia, powered directly by renewable energy.Envision Energy · Ulanqab, ChinaBuildingTarget 20272 GWSweetwater 1 and 2IREN 2 GW grid-connected site at Sweetwater, Texas; the first substation was energized in 2026 and initial AI capacity is planned for 2027.IREN · Sweetwater, TexasPaused1.8 GWCrusoe Wyoming (Project Jade)A 1.8 GW campus planned with Tallgrass in southeast Wyoming, paused indefinitely in June 2026 at an unnamed customer's request.Crusoe · Cheyenne area, Wyoming · 1 changeAnnounced1.6 GWFortune Data Center Park, near HyderabadFortune Hospitality & Infra plans a 1.6 GW hyperscale data center park on 200 acres next to Bharat Future City near Hyderabad.Fortune Hospitality & Infra · Hyderabad, India · $6.2BAnnounced1.5 GWRio AI City, JacarepaguaElea plans Rio AI City near Rio's Olympic Park, a 10-building campus of 1.5 GW scalable to 3.5 GW.Elea Data Centers · Rio de Janeiro, BrazilAnnounced1.5 GWYTL Power and JLand campus, JohorYTL Power and JLand plan a gigawatt-scale data center campus in Johor, estimated at 1.3 GW to 1.5 GW.YTL Power International · MalaysiaAnnouncedTarget 20271.44 GWWestern Downs Digital Park (Anthropic)Anthropic will lease part of Zerra DC's planned 1.44 GW Western Downs Digital Park near Dalby, Queensland, for inference.Zerra DC for Anthropic · Dalby, AustraliaAnnounced1.4 GWCDC Gregadoo campus, Wagga WaggaCDC is seeking approval for a 1.4 GW sovereign compute campus at Gregadoo near Wagga Wagga, pitched at about AUD 15 billion.CDC Data Centres · Wagga Wagga, Australia · $11BAnnounced1.4 GWMGX, Bpifrance, Mistral AI and Nvidia AI campus, Paris regionA joint venture of MGX, Bpifrance, Mistral AI and Nvidia plans Europe's largest AI campus in the Paris region, scaling to 1.4 GW.MGX · FranceBuildingTarget H2 20261.4 GWVantage Frontier campusTen buildings on 1,200 acres, 1.4 GW of GPU capacity, first building due in the second half of 2026. OpenAI named Shackelford County for an Oracle-developed Stargate site a month later.Vantage Data Centers · Shackelford County, Texas · $25BAnnouncedUnverified1.35 GWMonarch Compute CampusNscale bought the Monarch campus in Mason County, West Virginia, and signed a letter of intent to host up to 1.35 GW of Vera Rubin GPUs for Microsoft.Nscale for Microsoft · Point Pleasant, West Virginia · NVIDIA Vera Rubin NVL72Announced1.2 GWBell AI Fabric hub, SaskatchewanBell signed a non-binding MoU with Saskatchewan to add up to 900 MW of Bell AI Fabric capacity toward a 1.2 GW AI hub.Bell Canada · CanadaBuildingTarget 20271.2 GWNebius Independence AI factoryNebius broke ground in May 2026 on an owned AI factory in Independence, Missouri, planned for up to 1.2 GW.Nebius · Independence, MissouriAnnouncedTarget 20271.2 GWNebius Pennsylvania AI factoryNebius announced a second owned US gigawatt-scale site in Pennsylvania, with power secured for up to 1.2 GW, delivered in phases from 2027.Nebius · PennsylvaniaPartly onlineTarget 20301.2 GWSINES Data Campus (Start Campus)Start Campus is building a 1.2 GW campus at a former coal plant in Sines, where Nscale deploys over 66,000 Nvidia Rubin GPUs for Microsoft.Start Campus for Microsoft · Sines, Portugal · 12,600+ Nvidia Blackwell Ultra GPUs plus 66,000+ Nvidia Rubin GPUs · $10BPartly onlineTarget 20261.2 GWStargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.Oracle for OpenAI · Abilene, Texas · NVIDIA GB200 · 3 changesBuildingTarget Oct 15, 20261.2 GWStargate Milam County (Freebird)SB Energy builds and runs the 1.2 GW site; phase one, four data halls in 548,950 sq ft, is filed for completion on October 15, 2026.SB Energy for OpenAI · Milam County, Texas · 1 changeAnnounced1 GWBrookfield AI data center, CambraiBrookfield's EUR 20 billion French data center program is anchored by a mega-project in Cambrai.Brookfield Asset Management · Cambrai, FranceAnnouncedTarget Q3 20261 GWCrusoe Childress campusCrusoe and Lancium plan a 1 GW AI data center campus in Childress, Texas, for an unnamed hyperscaler, repeating their Abilene model.Crusoe · Childress, TexasBuildingTarget Jun 20271 GWData Center Valley, EkibastuzThe USD 10 billion Data Center Valley in Ekibastuz, Kazakhstan, backed by Nvidia and Firebird, is planned to scale to 1 GW.Firebird · Ekibastuz, Kazakhstan · $10BAnnouncedTarget 20301 GWDigital Connexion 1 GW campus, VisakhapatnamDigital Connexion, the Reliance, Brookfield and Digital Realty JV, plans a USD 11 billion, 1 GW campus on 400 acres near Visakhapatnam.Digital Connexion · Visakhapatnam, India · $11BAnnounced1 GWEdgeConneX campus, SkellefteaEdgeConneX plans to buy a Lyten site in Skelleftea, Sweden, that could become a campus of up to 1 GW.EdgeConneX · Skelleftea, SwedenAnnouncedTarget 20291 GWElsham Tech Park, North LincolnshireElsham Tech Park, a 1 GW AI data center campus on the former RAF Elsham Wolds airfield, received outline planning approval in March 2026.Greystoke · Elsham, United KingdomAnnouncedTarget 20261 GWFluidstack AI supercomputer, FranceFluidstack signed an MoU with the French government for a nuclear-powered AI supercomputer of up to 1 GW, with a EUR 10 billion first phase.Fluidstack · France · About 500,000 next-generation AI chips in phase 1AnnouncedTarget 20281 GWGoogle AI hub VisakhapatnamA $15 billion, 1 GW AI hub with AdaniConneX and Airtel; the first phase is expected by mid-2028.Google · Visakhapatnam, India · $15BBuilding1 GWMeta El PasoMeta's 29th data center, broken ground in October 2025 as a site that can scale to 1 GW.Meta · El Paso, Texas · $10B · 1 changeBuilding1 GWMeta Sturgeon County data centerMeta broke ground on a 1 GW AI-optimized data center in Sturgeon County, Alberta, its first in Canada, worth more than CAD 13 billion.Meta · Sturgeon County, CanadaPausedTarget May 20261 GWMicrosoft and G42 geothermal data center, OlkariaKenya suspended the USD 1 billion geothermal-powered data center planned with Microsoft and G42 at Olkaria over power needs.G42 for Microsoft · Naivasha, Kenya · $1BAnnouncedTarget Jun 2028Unverified1 GWMorris Technology ParkTract bought 343 acres in Morris, Illinois, for a 1 GW data center campus with ComEd power, first energization targeted for 2028.Tract · Morris, IllinoisBuildingTarget 20261 GWPrometheusMeta's first gigawatt AI supercluster, expected online in 2026.Meta · New Albany, OhioAnnounced1 GWStafford Technology CampusSTACK plans its largest development, the 1 GW-plus Stafford Technology Campus in Stafford County, Virginia.stack infrastructure · Stafford, VirginiaBuilding1 GWStargate Michigan (The Barn)Three 550,000 sq ft buildings developed by Related Digital; funding closed in April 2026 and all buildings were under construction by June.Oracle for OpenAI · Saline Township, Michigan · $10B · 1 changeBuildingTarget 20261 GWStargate UAEThe first 1 GW phase of the 5 GW UAE-US AI Campus, built by G42 with OpenAI, Oracle, Nvidia, Cisco and SoftBank. The UAE is now revising the campus into several sites.G42 for OpenAI · Abu Dhabi, United Arab Emirates · NVIDIA GB300 · $30B · 1 changeBuildingTarget 20281 GWStargate Wisconsin (Lighthouse)Four data centers with close to a gigawatt of AI capacity, developed by Vantage with Oracle for OpenAI; completion scheduled for 2028.Vantage Data Centers for OpenAI · Port Washington, Wisconsin · $15B · 1 changeAnnouncedTarget 2027 to 20291 GWSuperX AI computing park proposal, KazakhstanSuperX is in talks with Kazakhstan's government on a proposed 1 GW AI computing park, phased from 2027 to 2029.SuperX AI Technology · KazakhstanAnnouncedUnverified1 GWTCS HyperVault AI data center campus, HyderabadTCS subsidiary HyperVault secured 264 acres in Hyderabad for an AI data center campus of up to 1 GW, with up to INR 70,000 crore planned.TCS · Hyderabad, IndiaPartly online1 GWVantage South Wales campuses (Newport CWL1, Bridgend, Bro Tathan)Vantage plans more than 1 GW across Newport, Bridgend and Bro Tathan in the South Wales AI Growth Zone, with Nebius leasing capacity at CWL1.Vantage Data Centers for Nebius · Newport, United KingdomAnnounced1 GWZankore by Indosat AI factory platformIndosat, Ooredoo, Nokia and Nvidia launched Zankore, targeting 1 GW of Nvidia AI factory capacity in Indonesia.Indosat Ooredoo Hutchison · Indonesia · NvidiaOnlineTarget 2027946 MWColossus 2Operational from September 3, 2026 at about 946 MW of IT power, by Epoch AI's count the largest AI data center.SpaceXAI · Memphis, Tennessee · NVIDIA B200, B300 · 1 changeAnnouncedTarget 2027900 MWCloudHQ Queretaro campusCloudHQ plans a USD 4.8 billion, six-building campus in Queretaro with 900 MW planned and the first 200 MW of power secured.CloudHQ · Queretaro, Mexico · $4.8BAnnounced900 MWCrusoe Abilene expansion for MicrosoftMicrosoft leases 900 MW at Crusoe's Abilene campus, the capacity OpenAI and Oracle chose not to take when they stopped at 1.2 GW.Crusoe for Microsoft · Abilene, TexasPartly onlineTarget Q2 2026800 MWHeliosGalaxy converted its Helios bitcoin site in Dickens County, Texas, into an AI campus leased to CoreWeave; 133 MW of IT was delivered in Q2 2026.Galaxy Digital for CoreWeave · Dickens, TexasAnnouncedUnverified760 MWCyrusOne Freestone CountyCyrusOne plans a data center beside the Freestone Energy Center in Freestone County, Texas, with 380 MW contracted and 380 MW more in Phase 2.CyrusOne · Fairfield, TexasAnnounced750 MWBrookfield AI center, StrangnasBrookfield plans up to SEK 95 billion for a large AI center in Strangnas, Sweden, with capacity rising from 300 MW to 750 MW.Brookfield Asset Management · Strangnas, Sweden · $10BBuildingTarget Q1 2027704 MWBeacon PointHut 8 1 GW campus in Nueces County, Texas, fully leased as 704 MW of IT capacity to one unnamed high-investment-grade tenant.Hut 8 · Texas · Designed to NVIDIA DSX reference architectureAnnounced700 MWData4 Escaudain campusData4 launched a EUR 5 billion, 700 MW campus at the former Parc des Soufflantes site in Escaudain, northern France.Data4 · Escaudain, France · $5.8BAnnounced700 MWJurong Island data centre parkSingapore set aside 20 hectares on Jurong Island for a green data center park of up to 700 MW.JTC Corporation · Jurong Island, SingaporeAnnounced600 MWFirmus Project Southgate, South Australia (Tailem Bend, Stirling North)Firmus secured 600 MW of firm power from Gunvor for its first South Australian AI factory campuses at Tailem Bend and Stirling North.Firmus Technologies · Tailem Bend, AustraliaAnnouncedTarget H2 2027550 MWNEXTDC S7 AI campus with OpenAI, Eastern CreekNEXTDC plans a sovereign AI campus at its S7 site in Western Sydney with OpenAI as anchor tenant under OpenAI for Countries.NEXTDC for OpenAI · Eastern Creek, AustraliaAnnouncedTarget 2027550 MWPrime Data Centers ESB01, EsbjergPrime Data Centers and Brunswick Real Estate plan a 550 MW campus on Nordre Tovrupvej in Esbjerg, with a USD 2.3 billion first phase.Prime Data Centers · Esbjerg, Denmark · $2.3BAnnounced500 MWBell AI Fabric supercluster, British ColumbiaBell AI Fabric plans a hydro-powered AI data center supercluster in British Columbia of up to 500 MW across six facilities.Bell Canada · Kamloops, CanadaAnnouncedUnverified500 MWDakhla green data centerMorocco plans a 500 MW green data center in Dakhla powered by a dedicated solar and wind farm.Government of Morocco · Dakhla, MoroccoBuildingTarget Q4 2026500 MWDigital Edge CGK campus, BekasiDigital Edge topped out CGK1 at its USD 4.5 billion, 500 MW campus in Bekasi and signed a 1.45 GW power deal with PLN.Digital Edge · Bekasi, Indonesia · $4.5BAnnounced500 MWGoodman Project Atlas, Eastern CreekGoodman lodged plans for a 500 MW data center campus at its Eastern Creek site in western Sydney.Goodman Group · Eastern Creek, AustraliaAnnounced500 MWKhazna and Eni AI campus, Ferrera ErbognoneKhazna and Eni signed terms for a JV to build a 500 MW AI data center campus in Ferrera Erbognone, Lombardy, powered by a gas plant with CO2 capture.Khazna Data Centers · Ferrera Erbognone, ItalyAnnounced500 MWProject Jupiter hyperscale data center JV, GermanyWBS Power formed a JV to co-locate a 500 MW hyperscale data center with its Project Jupiter battery and solar site on a former German airfield.WBS Power · GermanyAnnounced500 MWSify 500 MW data centre, VisakhapatnamAndhra Pradesh granted Sify extra land for the second phase of its INR 15,266 crore, 500 MW data center project in Visakhapatnam.Sify Infinit Spaces · Visakhapatnam, India · $1.6BAnnounced500 MWSOS AI and cloud data center campus, BintanSOS signed a non-binding memorandum to potentially develop a 500 MW AI and cloud data center campus in Bintan, Indonesia.SOS Limited · Bintan, IndonesiaAnnounced500 MWStargate ArgentinaA letter of intent with Sur Energy under Argentina's large-investment regime; no exact site or construction start given.Sur Energy for OpenAI · Patagonia, Argentina · $25BAnnouncedUnverified500 MWxAI and HUMAIN data center, Saudi ArabiaHUMAIN and xAI plan a 500 MW data center in Saudi Arabia powered by Nvidia chips.HUMAIN for SpaceXAI · Saudi Arabia · NvidiaBuilding480 MWSDAIA Hexagon government data centre, RiyadhSDAIA began building the Hexagon data center in Riyadh, a Tier IV government facility planned at 480 MW.Saudi Data and Artificial Intelligence Authority · Riyadh, Saudi ArabiaBuildingTarget 2027430 MWatNorth FIN04 campus, MyllykoskiatNorth's FIN04 campus in Myllykoski, Kouvola, is planned to reach 430 MW, with YIT building its next facility.atNorth · Kouvola, FinlandBuildingTarget H2 2027401 MWJustified Data campusAnthropic signed a 20-year, $19 billion lease; first capacity in the second half of 2027, fully operational by early 2028.TeraWulf for Anthropic · Hawesville, KentuckyBuilding400 MWCyrusOne Bosque County (Thad Hill)CyrusOne is developing a data center campus powered through Calpine at the Thad Hill Energy Center in Bosque County, Texas, under 400 MW of agreements.CyrusOne · Meridian, TexasAnnounced400 MWNTT DATA and Neysa AI data center cluster, HyderabadNTT DATA, Neysa and Telangana signed an MoU for a 400 MW AI data center cluster in Hyderabad worth INR 10,500 crore.NTT DATA · Hyderabad, India · 25,000 GPUs · $1.2BPartly onlineTarget 2025400 MWPolaris Forge 1Applied Digital campus in Ellendale, North Dakota, leased to CoreWeave for 400 MW of critical IT load under roughly 15-year leases.Applied Digital for CoreWeave · Ellendale, North DakotaAnnouncedTarget 2028360 MWCoreWeave AI data centers, IndonesiaCoreWeave plans three AI data centers in Indonesia with 360 MW combined by 2028, its first in Asia-Pacific.CoreWeave · IndonesiaBuildingTarget 2028360 MWDataVolt Oxagon AI data center campusDataVolt is building a 360 MW first phase of an AI data center campus at Oxagon in NEOM, with HUMAIN co-developing the first 100 MW due in 2028.DataVolt · Oxagon, NEOM, Saudi ArabiaAnnounced360 MWDayOne and Firmus AI campus, Kabil, BatamDayOne and Firmus are developing a 360 MW AI campus in Batam, with access to up to 170,000 Nvidia accelerators.DayOne for Firmus Technologies · Batam, Indonesia · Up to 170,000 Nvidia acceleratorsPartly onlineTarget H2 2026360 MWLake MarinerTeraWulf is converting its Lake Mariner campus in western New York into AI halls leased to Fluidstack, with Google backstopping the leases.TeraWulf for Fluidstack · Barker, New YorkAnnounced354 MWAirTrunk MEL2, MelbourneAirTrunk bought a site in Melbourne's north-west for MEL2, a 354 MW campus worth more than AUD 5 billion.AirTrunk · Melbourne, AustraliaAnnouncedTarget 2028350 MWatNorth NOR01, Haugaland Business ParkatNorth bought a 36-hectare plot in Haugaland Business Park for NOR01, its first Norwegian site, starting at 120 MW and scaling to 350 MW.atNorth · Gismarvik, NorwayPaused330 MWImperial Valley data centerA proposed 330 MW data center near Imperial, California; a judge tentatively ruled in Sep 2026 that a full environmental review is required first.Imperial Valley Computer Manufacturing · Imperial, CaliforniaAnnouncedTarget 2027310 MWNebius AI Factory, LappeenrantaNebius plans a 310 MW AI factory in Lappeenranta, Finland, investing USD 10 billion, with customer availability expected in 2027.Nebius · Lappeenranta, Finland · $10BBuilding300 MWAirTrunk TOK1 expansion, East TokyoAirTrunk secured a USD 1.2 billion green loan to expand its TOK1 campus in East Tokyo, designed to scale past 300 MW.AirTrunk · Tokyo, Japan · $1.2BAnnouncedTarget H1 2028300 MWatNorth Hamre 1, SollefteaatNorth plans a 300 MW data center on the 50-hectare Hamre 1 site in Solleftea, Sweden, due in the first half of 2028.atNorth · Solleftea, SwedenBuildingTarget Sep 2026300 MWBarber LakeCipher is building an AI data center at Barber Lake near Colorado City, Texas, leased for 10 years to Fluidstack with a Google backstop.Cipher Digital for Fluidstack · Colorado City, TexasBuildingTarget Oct 2026300 MWBlack PearlCipher is converting its Black Pearl site in Wink, Texas, into a 300 MW AI data center leased to Amazon Web Services for 15 years.Cipher Digital for AWS · Wink, TexasAnnouncedTarget 2030300 MWClearstone Ebbsfleet AI Data Center campusClearstone plans a 300 MW AI data center campus near Ebbsfleet, Kent, targeting operation in 2030.Clearstone · Ebbsfleet, United KingdomAnnouncedTarget 2031300 MWEdgeConneX campuses, Lodi and south MilanItaly named EdgeConneX's EUR 3 billion plan for three Lombardy campuses, over 300 MW combined by 2031, a project of strategic national interest.EdgeConneX · Lodi, Italy · $3.5BPartly onlineTarget 2027300 MWFirebird AI factory, ArmeniaFirebird launched an Nvidia AI factory in Armenia and plans 300 MW and more than 70,000 GPUs there by end 2027.Firebird · Armenia · More than 70,000 Nvidia Rubin and Blackwell GPUsPartly online300 MWNebius VinelandDeveloped by DataOne for Nebius to serve its $17 billion Microsoft deal; New Jersey fined it over $1 million in September 2026 for unpermitted gas generators.Nebius for Microsoft · Vineland, New Jersey · 1 changeAnnouncedTarget Q1 2028300 MWNFD Korea AI campus, DangjinNFD Korea is developing a 300 MW AI data center campus in Dangjin with site, permits and a 300 MW KEPCO supply deal secured.NFD Korea · Dangjin, South KoreaPartly online300 MWODATA QR03 campus, QueretaroODATA opened the first 72 MW building of its QR03 campus in Queretaro, planned at up to 300 MW and more than USD 3 billion.ODATA · Queretaro, Mexico · $3BBuildingTarget FY2026300 MWSoftBank Hokkaido Tomakomai AI Data CenterSoftBank is building an AI data center in Tomakomai, Hokkaido, with a 50 MW first phase due in fiscal 2026 and 300 MW planned.SoftBank · Tomakomai, JapanBuilding300 MWVantage JHB1 campus (ex-Yondr), Sedenak Tech ParkVantage acquired Yondr's 300 MW hyperscale campus in Sedenak Tech Park, Johor, which will host three data centers when complete.Vantage Data Centers · Kulai, MalaysiaAnnouncedUnverified280 MWAirTrunk JHB3 and JHB4, Iskandar PuteriAirTrunk plans two new hyperscale campuses, JHB3 and JHB4, in Iskandar Puteri, Johor, adding 280 MW for MYR 12 billion.AirTrunk · Iskandar Puteri, Malaysia · $3BAnnouncedTarget 2028280 MWDatagrid Data Centre Park, MakarewaDatagrid received consent for a 280 MW data center park at Makarewa near Invercargill, New Zealand's largest, due to open in 2028.Datagrid · Makarewa, New ZealandBuildingTarget 2026280 MWPolaris Forge 2A $3 billion, 280 MW AI campus near Harwood, North Dakota, with 200 MW leased to an unnamed investment-grade hyperscaler.Applied Digital · Harwood, North Dakota · $3BPartly online260 MWDenton HPC campusCore Scientific is converting its Denton, Texas, site into a roughly 260 MW GPU data center leased to CoreWeave.Core Scientific for CoreWeave · Denton, Texas · NVIDIA GPUsBuildingTarget Q2 2027245 MWRiver BendHut 8 campus in West Feliciana Parish, Louisiana, with a 245 MW IT lease to Fluidstack for Anthropic, backstopped by Google.Hut 8 for Fluidstack · St. Francisville, LouisianaPartly onlineTarget May 2026241 MWRiot Rockdale data center campusRiot is turning its Rockdale, Texas, bitcoin site into AI data centers, leased to AMD and to an unnamed frontier AI lab for 191 MW.Riot Platforms · Rockdale, TexasBuildingTarget Q3 2026240 MWNscale Ward County campusNscale is deploying about 104,000 NVIDIA GB300 GPUs for Microsoft at a roughly 240 MW campus in Ward County, Texas, leased from Ionic Digital.Nscale for Microsoft · Barstow, Texas · About 104,000 NVIDIA GB300; later Vera RubinBuilding240 MWPDG JC4 campus, BekasiPDG started building JC4 in Greenland International Industrial Center, Bekasi, a 240 MW campus of four buildings.Princeton Digital Group · Bekasi, IndonesiaBuildingTarget 2026230 MWNscale Narvik (was Stargate Norway)Built by Nscale for an Nscale and Aker joint venture on hydropower. OpenAI announced it as Stargate Norway, then did not sign; Microsoft took the capacity.Nscale for Microsoft · Narvik, Norway · NVIDIA Rubin (30,000 for Microsoft) · 1 changeBuildingTarget Q2 2026224 MWVantage NV1Vantage is building a 224 MW, four-building AI campus in Storey County outside Reno, Nevada, with the first two buildings leased.Vantage Data Centers · McCarran, Nevada · $3BAnnounced220 MWSTACK South Dallas campusSTACK plans a 220 MW, AI-ready campus on over 100 acres in Lancaster, south of Dallas, Texas, with dedicated power.stack infrastructure · Lancaster, TexasAnnouncedTarget Q1 2028210 MWDelta Forge 2Applied Digital fifth AI campus, 210 MW leased to an unnamed hyperscaler; DCD reports it will be a $3.2 billion build in Alabama.Applied Digital · Alabama · $3.2BBuildingTarget 2027200 MWByteDance data center, PecemOmnia is building a data center for ByteDance at the Pecem port complex in Ceara, planned at 200 MW and possibly near 1 GW.Omnia for ByteDance · Sao Goncalo do Amarante, Brazil · $38BPartly onlineTarget 2026200 MWChildress Horizon 1-4IREN is building four liquid-cooled halls at Childress, Texas, to host NVIDIA GB300 GPUs for Microsoft under a $9.7 billion contract.IREN for Microsoft · Childress, Texas · NVIDIA GB300 · $5.8BBuilding200 MWCyrusOne DFW7CyrusOne is building the 200 MW DFW7 campus in Fort Worth, Texas, next to an Eolian battery storage site to reuse its grid connection.CyrusOne · Fort Worth, TexasAnnounced200 MWEarlham Gigagrid offshore data center, North SeaOrcadian Energy began assessing an offshore power station and 200 MW data center on the Earlham gas discovery in the Southern North Sea.Orcadian Energy · United KingdomAnnouncedUnverified200 MWEgypt AI data center (Vodafone, Elsewedy, Cassava)Egypt plans a 200 MW, USD 1 billion AI data center with Nvidia technology, starting with a 20 MW phase by Vodafone, Elsewedy and Cassava.Cassava Technologies · Egypt · Nvidia · $1BBuilding200 MWLG Uplus Paju AI Data CenterLG Uplus is building a 200 MW hyperscale AI data center in Paju, Gyeonggi, with five buildings.LG Uplus · Paju, South KoreaAnnouncedTarget 2026200 MWMicrosoft and G42 200 MW expansion via Khazna, UAEMicrosoft and G42 are adding 200 MW of data center capacity in the UAE through Khazna, starting to come online before end 2026.Khazna Data Centers for Microsoft · Abu Dhabi, United Arab EmiratesPartly onlineTarget 2027200 MWMistral AI compute sites, EssonneMistral AI runs a 40 MW training site at Bruyeres-le-Chatel and is adding sites in Essonne within a EUR 4 billion compute program.Mistral AI · Bruyeres-le-Chatel, France · $4.6BAnnouncedTarget 2028200 MWNAVER GAK Sejong AI factoryNAVER plans to grow its Nvidia AI factory at GAK Sejong from 55 MW to 200 MW by 2028, with Brookfield financing up to USD 9 billion.NAVER · Sejong, South Korea · Nvidia Vera Rubin and BlackwellBuildingTarget 2027200 MWSchwarz Digits data center, LubbenauLidl owner Schwarz Group is building an EUR 11 billion AI data center in Lubbenau with about 200 MW in phase one and up to 100,000 GPUs.Schwarz Digits · Lubbenau, Germany · Up to 100,000 GPUsAnnounced200 MWSGI-HCM AI data center campus, Cu ChiKinh Bac City and Accelerated Infrastructure Capital plan a USD 2 billion, 200 MW AI data center campus in Cu Chi, Ho Chi Minh City.Kinh Bac City Development · Cu Chi, Vietnam · $2BBuildingTarget Late 2025192 MWVantage OH1Vantage broke ground on a 192 MW hyperscale campus in New Albany, Ohio, its first in the Midwest, investing over $2 billion.Vantage Data Centers · New Albany, Ohio · $2BBuildingTarget Late 2027192 MWVantage VA4Vantage is investing $2 billion in a 192 MW, three-building campus in Stafford County near Fredericksburg, Virginia.Vantage Data Centers · Stafford, Virginia · $2BBuildingTarget H2 2026168 MWAbernathy AI campusA Fluidstack and TeraWulf joint venture building 168 MW of AI capacity at Abernathy, Texas; TeraWulf agreed in July 2026 to sell its stake to Fluidstack.Fluidstack · Abernathy, TexasAnnounced168 MWReliance AI data center for Meta, JamnagarReliance will build a 168 MW AI data center in Jamnagar that Meta will lease, its first in India.Reliance Industries for Meta · Jamnagar, IndiaBuilding165 MWCompute Nordic AI campus, Mikkeli (Cerebras)Compute Nordic is building a 165 MW AI data center in Mikkeli, Finland, under seven-year contracts with Cerebras.Compute Nordic for Cerebras · Mikkeli, FinlandAnnounced150 MWDPS AI data center with Alibaba affiliate, MelakaDPS Resources signed an MoU with an Alibaba affiliate to explore an AI data center in Melaka, with a first phase of about 150 MW to 180 MW.DPS Resources Berhad · Melaka, Malaysia · $1.1BAnnouncedTarget 2027150 MWEcoDataCenter campus, SmedjebackenEcoDataCenter agreed to buy 52 hectares in Smedjebacken for a 150 MW campus, its third in Sweden.EcoDataCenter · Smedjebacken, SwedenAnnouncedTarget 2025150 MWSoftBank AI data center, Sharp Sakai plantSoftBank plans a large AI data center at the former Sharp Sakai LCD plant, starting above 150 MW and growing past 400 MW.SoftBank · Sakai, JapanBuildingTarget 2026 to 2029150 MWTELUS sovereign AI factory cluster, British ColumbiaTELUS plans three sovereign AI data centers in British Columbia, scaling to more than 150 MW by 2032, after its Rimouski AI Factory sold out.TELUS · Vancouver, Canada · Nvidia GPUsAnnouncedTarget 2029144 MWCyrusOne Jack County campusCyrusOne plans two data centers with at least 144 MW of IT in Jack County, Texas, starting on on-site gas power.CyrusOne · Jacksboro, TexasAnnounced144 MWEchelon Iberdrola Madrid Sur campusThe Echelon and Iberdrola JV's first project is Madrid Sur, a 144 MW data center complex with a 230 MW grid connection.Echelon Data Centres · Madrid, SpainAnnounced144 MWSTACK Loudoun County 144 MW campusSTACK plans a 144 MW hyperscale data center campus in Loudoun County, Virginia.stack infrastructure · VirginiaAnnounced135 MWGoodman Project Apollo, Macquarie ParkNSW approved Goodman's AUD 1.4 billion, 135 MW Project Apollo data center in Macquarie Park, northern Sydney.Goodman Group · Macquarie Park, Australia · $1BAnnounced129 MWVOLT AI factory, DubaiVOLT and Dubai Integrated Economic Zones plan an AI factory in Dubai with 29 MW initially and 100 MW more committed.VOLT Data Centers · Dubai, United Arab EmiratesAnnounced128 MWTikTok data center, LahtiTikTok plans a second Finnish data center in Lahti, a EUR 1 billion project starting at 50 MW and expandable to 128 MW.TikTok · Lahti, Finland · $1.16BAnnounced121 MWTydal Data Center, NorwayBitdeer signed a USD 4.7 billion lease with Volta for 121 MW of IT capacity at its Tydal facility in Norway for a leading AI lab.Bitdeer for Volta · Tydal, Norway · Nvidia GPUsBuildingTarget 2027120 MWBDx AI Campus 2 (CGK4), West JavaBDx broke ground on its CGK4 AI campus in West Java, where the first of six buildings will deliver 120 MW.BDx Data Centers · IndonesiaBuildingTarget Q4 2026120 MWPDG JC3 campus, Greater JakartaPDG broke ground on JC3, a USD 1 billion, 120 MW hyperscale and AI campus near Jakarta.Princeton Digital Group · Bekasi, Indonesia · $1BBuildingTarget H2 2026120 MWReliance multi-gigawatt AI data centers, JamnagarReliance has begun building multi-gigawatt AI data centers in Jamnagar, with over 120 MW due online in the second half of 2026.Reliance Industries · Jamnagar, India · $110BBuildingUnverified120 MWYotta D4, Greater NoidaYotta is starting construction of a 120 MW data center in Greater Noida to host 40,000 Nvidia Vera Rubin GPUs.Yotta Data Services · Greater Noida, India · 40,000 Nvidia Vera Rubin GPUsBuildingTarget 2026100 MWAMD, Cisco and HUMAIN AI infrastructure JVAMD, Cisco and HUMAIN formed a JV to deliver up to 1 GW of AI infrastructure in Saudi Arabia by 2030, starting with 100 MW.HUMAIN · Saudi Arabia · AMD Instinct MI450 Series GPUsAnnounced100 MWCoreWeave LancasterCoreWeave committed up to $6 billion to equip an AI data center in Lancaster, Pennsylvania, starting at 100 MW with room for 300 MW.CoreWeave · Lancaster, Pennsylvania · $6BAnnouncedTarget Q4 2026100 MWDigital Edge DC EEC project, ThailandDigital Edge and B.Grimm Power formed a JV and unveiled a 100 MW, USD 1 billion data center in Thailand's Eastern Economic Corridor.Digital Edge · Thailand · $1BAnnounced100 MWFoxconn and Nvidia AI factory, KaohsiungFoxconn and Nvidia plan an AI data center in Taiwan targeted at 100 MW, built in phases with some in Kaohsiung.Foxconn · Kaohsiung, Taiwan · NvidiaBuildingTarget Q2 2026100 MWHUMAIN data centers, Riyadh and DammamHUMAIN broke ground on AI data centers in Riyadh and Dammam with up to 100 MW initially, using Nvidia chips, as part of a 1.9 GW plan.HUMAIN · Riyadh, Saudi Arabia · 18,000 Nvidia chips approved locallyAnnounced100 MWKhazna AI-ready data center, AnkaraKhazna secured a site in Baskent OIZ, Ankara, for an AI-ready data center of up to 100 MW.Khazna Data Centers · Ankara, TürkiyeAnnounced100 MWStargate India (OpenAI and Tata HyperVault)OpenAI will be the first customer of TCS HyperVault, starting with 100 MW of AI data center capacity in India and aiming for 1 GW.TCS for OpenAI · IndiaBuildingTarget Q1 202790 MWNscale AI Campus, Loughton (Microsoft)Nscale is building a GBP 2 billion AI campus in Loughton with Microsoft as anchor tenant, 50 MW scalable to 90 MW, though grid power is delayed.Nscale for Microsoft · Loughton, United Kingdom · 23,040 Nvidia GB300 GPUs initiallyBuildingTarget Dec 202650 MWAWS Saudi Arabia Region and HUMAIN AI ZoneAWS will launch its first Saudi cloud region by December 2026 with a USD 5.3 billion investment and deliver up to 50 MW in HUMAIN's AI Zone.AWS · Saudi Arabia · AWS Trainium and Nvidia · $5.3BAnnouncedTarget 2028 to 202950 MWScala AI City, Eldorado do SulScala plans an AI campus in Eldorado do Sul starting at 50 MW and aiming for up to 5 GW, with operations expected around 2028.Scala Data Centers · Eldorado do Sul, Brazil · $0.5BAnnouncedTarget 202736 MWNexus AI Factory, MoroccoNexus Core Systems signed an MoU to invest MAD 12 billion in a two-phase AI factory in Morocco, starting in Nouaceur.Nexus Core Systems · Nouaceur, Morocco · $1.29BAnnouncedNot statedAMACO off-grid AI data center, MombasaGreek firm AMACO is seeking approval for a USD 1.5 billion off-grid AI data center in Mombasa, Kenya.AMACO Energy Group · Mombasa, Kenya · $1.5BBuildingNot statedAWS Asia Pacific (Hyderabad) Region expansionAWS broke ground on a new data center to expand its Hyderabad region, part of a planned USD 7 billion investment in Telangana.AWS · Hyderabad, India · $7BOnlineTarget Sep 1, 2025Not statedAWS Asia Pacific (New Zealand) Region, AucklandAWS opened its New Zealand region with three availability zones, backed by an NZD 7.5 billion investment.AWS · Auckland, New ZealandAnnouncedNot statedAWS Butts and Douglas countiesAWS plans at least $11 billion for data centers in Butts and Douglas counties, Georgia, to support AI and cloud.AWS · Jackson, Georgia · $11BBuildingTarget 2026UnverifiedNot statedAWS Chile cloud region, SantiagoAWS is nearing launch of its Chile region, with sites in Huechuraba, Padre Hurtado and Lampa and a USD 4 billion commitment.AWS · Santiago, Chile · $4BPartly onlineTarget 2035Not statedAWS Europe (Spain) Region expansion, AragonAmazon raised its Spain investment to EUR 33.7 billion through 2035, expanding AWS data centers in Aragon including Huesca, Zaragoza and Teruel.AWS · Zaragoza, Spain · $40BAnnouncedNot statedAWS Hinds County (former Delphi plant)Amazon is converting the former Delphi manufacturing plant in Hinds County, Mississippi, into a $1 billion data center.AWS · Clinton, Mississippi · $1BPartly onlineNot statedAWS Madison County campusesAWS data center complexes in two Madison County, Mississippi, industrial parks; the 2024 $10 billion plan grew by $11 billion in 2026.AWS · Canton, Mississippi · $21BOnlineTarget Jan 14, 2025Not statedAWS Mexico (Central) Region, QueretaroAWS opened its Mexico (Central) Region in Queretaro with three availability zones, planning over USD 5 billion over 15 years.AWS · Queretaro, Mexico · $5BAnnouncedUnverifiedNot statedAWS Montgomery County campusAmazon plans a multibillion-dollar data center campus in Montgomery County, Missouri, with over 400 full-time jobs.AWS · Montgomery City, MissouriAnnouncedNot statedAWS northwest Louisiana campusesAmazon plans three data center campuses across Caddo and Bossier parishes and Shreveport, Louisiana, now an $18 billion plan.AWS · Shreveport, Louisiana · $18BAnnouncedTarget End 2030Not statedAWS Ohio expansion (Fayette County first site)AWS plans $10 billion of new Ohio data center investment through 2030, starting with about $5 billion in Fayette County.AWS · Washington Court House, Ohio · $10BBuildingNot statedAWS Pennsylvania campusesAmazon's $20 billion Pennsylvania plan, starting with AI data center campuses in Salem Township and Falls Township.AWS · Salem Township and Falls Township, Pennsylvania · $20BBuildingNot statedAWS Richmond CountyA $10 billion AWS campus; state air permits came in August 2026, and regulators rejected Duke Energy's gas turbines for it in September.AWS · Richmond County, North Carolina · $10B · 2 changesAnnouncedTarget 2027Not statedAWS Tokyo and Osaka region expansionAWS plans JPY 2.26 trillion through 2027 to expand its data center capacity in Tokyo and Osaka.AWS · Tokyo, Japan · $15BAnnouncedNot statedAWS Warren County campusAmazon plans at least $3 billion for an AI and cloud data center campus in Warren County, Mississippi.AWS · Vicksburg, Mississippi · $3BAnnouncedNot statedBlackstone data centers, AragonBlackstone plans to invest EUR 7.5 billion in data centers in Aragon, Spain, to lease to tenants.Blackstone · Zaragoza, Spain · $8.2BOnlineNot statedColossusBuilt in 122 days, then doubled to 200,000 GPUs in 92 days. xAI now trades as SpaceXAI.SpaceXAI · Memphis, Tennessee · 200,000 NVIDIA GPUsBuildingNot statedCompass Hoffman Estates campus (former Sears HQ)Compass is turning the former Sears headquarters in Hoffman Estates, Illinois, into a five-building hyperscale campus worth about $10 billion.Compass Datacenters · Hoffman Estates, Illinois · $10BBuildingNot statedCompass Meridian campusCompass is building an eight-building hyperscale campus in Meridian, Mississippi, a $10 billion investment at full fit-out.Compass Datacenters · Meridian, Mississippi · $10BAnnouncedNot statedCyrusOne Lee County campusCyrusOne plans a multi-phase data center campus in Lee County, North Carolina, projected at about $7 billion at full buildout.CyrusOne · Sanford, North Carolina · $7BAnnouncedNot statedCyrusOne Medina County campusCyrusOne plans a multi-phase data center project in Medina County, Texas, expected to cost about $4 billion to $6 billion.CyrusOne · Hondo, Texas · $4BAnnouncedNot statedCyrusOne Sulphur Springs campusCyrusOne is evaluating a phased campus in Sulphur Springs, Texas, that could reach $5 billion to $10 billion if fully built.CyrusOne · Sulphur Springs, Texas · $5BBuildingNot statedCyrusOne Yorkville Technology CampusCyrusOne is developing a technology campus in Yorkville, Illinois, approved in 2024, with more than $1 billion of planned investment.CyrusOne · Yorkville, Illinois · $1BBuildingTarget 2027Not statedDayOne hyperscale data centre, LahtiDayOne is investing EUR 1.2 billion in a hyperscale data center on a former industrial site in Kiverio, Lahti, ready in 2027.DayOne · Lahti, FinlandAnnouncedTarget Early 2026Not statedDeutsche Telekom and Nvidia Industrial AI Cloud, MunichDeutsche Telekom and Nvidia set up a EUR 1 billion AI factory in Munich with up to 10,000 Blackwell GPUs for German industry.Deutsche Telekom · Munich, Germany · Up to 10,000 Nvidia Blackwell GPUs · $1.15BBuildingNot statedEchelon LIN10, MilanEchelon and Starwood Capital bought a 37-acre site near Milan for LIN10, a EUR 3 billion campus with 250 MVA of capacity.Echelon Data Centres · Milan, Italy · $3.5BOnlineNot statedFairwater AtlantaThe second Fairwater site, linked to Wisconsin over Microsoft's AI WAN so one training job can span both.Microsoft · Atlanta, Georgia · NVIDIA GB200, GB300OnlineTarget 2026Not statedFairwater WisconsinThree buildings on 315 acres run as one supercomputer; fully operational in June 2026, with a second facility under construction next door.Microsoft · Mount Pleasant, Wisconsin · NVIDIA GB200 · $7.3B · 2 changesAnnouncedTarget Early 2030sNot statedForestalia Bufalo Project (Magallon, Botorrita, Alfamen)Forestalia plans EUR 12 billion for three data centers in Zaragoza province at Magallon, Botorrita and Alfamen, known as the Bufalo Project.Forestalia · Magallon, Spain · $14BAnnouncedNot statedG42, FPT and Viet Thai data centers, VietnamG42, FPT and Viet Thai Group signed a framework to build three data centers in Vietnam with up to USD 1 billion in consumption commitments.G42 · VietnamAnnouncedNot statedGoogle and Turkcell hyperscale region, TurkiyeGoogle and Turkcell plan to invest USD 3 billion in Turkiye's first hyperscale cloud region data center.Google · Türkiye · $3BAnnouncedNot statedGoogle Cedar Rapids data centerGoogle is investing $7 billion in Iowa, including a new data center in Cedar Rapids and expansion in Council Bluffs.Google · Cedar Rapids, Iowa · $7BAnnouncedNot statedGoogle Chesterfield County data centerGoogle is investing $9 billion in Virginia through 2026, including a new data center in Chesterfield County.Google · Chesterfield, Virginia · $9BAnnouncedNot statedGoogle Cloud and PIF AI hub, Saudi ArabiaGoogle Cloud and PIF are building a USD 10 billion global AI hub in Saudi Arabia, to launch with HUMAIN.Google · Saudi Arabia · $10BBuildingNot statedGoogle data center and cloud region, Elmina Business ParkGoogle broke ground on its first Malaysian data center and cloud region at Elmina Business Park, Selangor, a USD 2 billion investment.Google · Shah Alam, Malaysia · $2BAnnouncedNot statedGoogle data center, ChonburiGoogle's USD 1 billion Thailand plan includes a data center in Chonburi and a cloud region in Bangkok.Google · Chonburi, Thailand · $1BAnnouncedTarget 2029Not statedGoogle data center, DietzenbachGoogle will build a new data center in Dietzenbach and keep expanding Hanau as part of a EUR 5.5 billion German investment through 2029.Google · Dietzenbach, GermanyAnnouncedTarget 2027 to 2028Not statedGoogle data centers, Finland (Hamina, Kajaani, Muhos, Vaala)Google plans at least EUR 13 billion in Finnish data center and supporting infrastructure in Hamina, Kajaani, Muhos and Vaala over 2027 to 2028.Google · Hamina, FinlandBuildingNot statedGoogle Dorchester County sites and Berkeley County expansionGoogle is investing $9 billion in South Carolina to expand its Berkeley County campus and build two new sites in Dorchester County.Google · Ridgeville, South Carolina · $9BAnnouncedNot statedGoogle Jackson County campus expansionGoogle is spending $1.5 billion to expand its data center campus on a former coal plant site in Jackson County, Alabama.Google · Stevenson, Alabama · $1.5BAnnouncedTarget 2027Not statedGoogle St. Ghislain campus expansionGoogle will invest EUR 5 billion in 2026 and 2027 to expand its St. Ghislain data center campus in Belgium.Google · Saint-Ghislain, BelgiumAnnouncedNot statedGoogle Stillwater campusGoogle is investing $9 billion in Oklahoma, including a new data center campus in Stillwater and expansion of its Pryor site.Google · Stillwater, Oklahoma · $9BBuildingTarget 2027Not statedGoogle Texas campusesGoogle's $40 billion Texas investment through 2027, including new data center campuses in West Texas.Google · Haskell and Armstrong counties, Texas · $40BAnnouncedNot statedGoogle West Memphis data centerGoogle plans a $4 billion investment in Arkansas, including its first data center in the state, in West Memphis.Google · West Memphis, Arkansas · $4BBuildingNot statedMeta Beaver Dam Data CenterMeta is building a 700,000 square foot AI-optimized data center in Beaver Dam, Wisconsin, a $1 billion investment.Meta · Beaver Dam, Wisconsin · $1BAnnouncedNot statedMeta Eagle Mountain expansionMeta is expanding its Eagle Mountain, Utah, data center, lifting its total Utah investment to more than $3 billion.Meta · Eagle Mountain, Utah · $3BAnnouncedNot statedMeta Lebanon Data CenterMeta plans a roughly 4 million square foot data center campus in Lebanon, Indiana, an investment of more than $10 billion.Meta · Lebanon, Indiana · $10BBuildingNot statedMeta Montgomery Data CenterMeta data center in Montgomery, Alabama; a 2025 expansion added two buildings and raised the investment to over $1.5 billion.Meta · Montgomery, Alabama · $1.5BAnnouncedNot statedMeta Tulsa Data CenterMeta plans an AI data center in Tulsa, Oklahoma, representing more than $1 billion of investment.Meta · Tulsa, Oklahoma · $1BAnnouncedTarget 2028Not statedMicrosoft cloud and AI infrastructure, ThailandMicrosoft plans more than USD 1 billion in cloud and AI infrastructure and operations in Thailand from 2026 to 2028.Microsoft · Thailand · $1BOnlineTarget Aug 2026Not statedMicrosoft India South Central region, HyderabadMicrosoft opened its Hyderabad data center region, its largest in India, as part of a USD 17.5 billion investment in the country over 2026 to 2029.Microsoft · Hyderabad, India · $18BAnnouncedNot statedMicrosoft Indonesia Central cloud regionMicrosoft will invest USD 1.7 billion over four years in new cloud and AI infrastructure in Indonesia.Microsoft · Jakarta, Indonesia · $1.7BBuildingNot statedMicrosoft Rhein-Erft data center cluster (Bergheim, Bedburg, Elsdorf)Microsoft is building a data center cluster in the Rhenish mining region at Bergheim, Bedburg and Elsdorf as part of a EUR 3.2 billion plan.Microsoft · Bergheim, GermanyAnnouncedUnverifiedNot statedMicrosoft Sao Paulo datacenter campuses expansionMicrosoft plans BRL 14.7 billion over three years to expand cloud and AI infrastructure across several datacenter campuses in Sao Paulo state.Microsoft · Sao Paulo, BrazilAnnouncedNot statedMicrosoft Sweden Central expansion (Gavle, Sandviken, Staffanstorp)Microsoft will spend SEK 33.7 billion over two years to expand its Swedish data centers in Gavle, Sandviken and Staffanstorp and add 20,000 GPUs.Microsoft · Gavle, Sweden · 20,000 GPUs · $3.2BAnnouncedNot statedMicrosoft West Denmark datacenter regionMicrosoft plans a second Danish datacenter region in West Denmark, a multi-billion dollar investment beyond 2027.Microsoft · DenmarkAnnouncedNot statedMistral AI and EcoDataCenter AI data center, BorlangeMistral AI and EcoDataCenter will invest EUR 1.2 billion in an AI data center at EcoDataCenter's Borlange site, Mistral's first outside France.EcoDataCenter for Mistral AI · Borlange, Sweden · $1.42BAnnouncedUnverifiedNot statedOracle cloud region, MalaysiaOracle plans to invest more than USD 6.5 billion to open a public cloud region in Malaysia.Oracle · Malaysia · $6.5BBuildingTarget 2028Not statedProject Jupiter (Stargate New Mexico)The Oracle-developed Stargate site near the US-Mexico border. The gas pipeline was refused twice, and in September 2026 Oracle sent a force majeure notice.Oracle for OpenAI · Santa Teresa, Doña Ana County, New Mexico · 1 changeOnlineNot statedProject RainierAn EC2 UltraCluster of Trainium2 servers built mainly for Anthropic's Claude, fully operational less than a year after it was announced.AWS for Anthropic · New Carlisle, Indiana · AWS Trainium2 (nearly 500,000)AnnouncedNot statedProposed AWS Region, PhilippinesAWS discussed with President Marcos a proposed Philippine AWS Region that could bring up to USD 5 billion over 15 years.AWS · Philippines · $5BBuildingNot statedQTS Cambois campus, former Blyth Power StationBlackstone's QTS is developing a GBP 10 billion data center campus at the former Blyth Power Station site in Cambois, with phase one approved.QTS Data Centers · Cambois, United KingdomAnnouncedNot statedQTS Hall County campusQTS will build and operate data centers on Lancium land near Turkey in Hall County, Texas, with more than $10 billion expected.QTS Data Centers · Turkey, Texas · $10BAnnouncedNot statedRangeIDC AI data center, Nongsa, BatamChina's RangeIDC plans a USD 5 billion AI data center on a 30-hectare site in Nongsa, Batam, built by PT Equator Gate System Batam.Range Intelligent Computing Technology · Batam, Indonesia · $5BAnnouncedNot statedRubix AI data center, FlixSubmer's Rubix Data Centers plans a more than EUR 1 billion AI data center at an industrial site in Flix, Catalonia.Rubix Data Centers · Flix, Spain · $1.14BBuildingNot statedSK AI Data Center UlsanSK Group and AWS are building an AI data center in Ulsan's national industrial complex at an estimated KRW 7 trillion.SK Telecom for AWS · Ulsan, South Korea · $5.2BBuildingTarget 2026Not statedStargate LordstownSoftBank's advanced data center design, broken ground in 2025 and due to be operational in 2026; with Milam County it can scale to 1.5 GW.SoftBank for OpenAI · Lordstown, OhioPausedTarget Q1 2026Not statedStargate UKSovereign compute with Nvidia and Nscale in North East England. OpenAI paused it in April 2026, citing energy costs and regulation.Nscale for OpenAI · Cobalt Park, North Tyneside, United Kingdom · Up to 8,000 NVIDIA GPUs, scaling to 31,000 · 1 changeBuildingNot statedSTT Johor campus, Iskandar PuteriSTT GDC secured USD 1.37 billion of financing to develop STT Johor, its flagship Malaysia campus at Nusa Cemerlang Industrial Park.STT GDC · Iskandar Puteri, MalaysiaAnnouncedNot statedTikTok data centers, ThailandThailand's Board of Investment approved TikTok data centers in Bangkok, Samut Prakan and Chachoengsao worth about USD 25 billion.TikTok · Bangkok, Thailand · $25BAnnouncedNot statedVantage campus, Villanueva de GallegoVantage plans a EUR 3.2 billion, five-phase data center campus on 40 hectares in Villanueva de Gallego near Zaragoza.Vantage Data Centers · Villanueva de Gallego, Spain · $3.78BAnnouncedUnverifiedNot statedWonder Valley data centre park, GreenviewWonder Valley is a proposed CAD 70 billion AI data center park backed by Kevin O'Leary on the Greenview Industrial Gateway in Alberta.O'Leary Ventures · Municipal District of Greenview, Canada

Questions

What counts as a build?

An announced AI data center campus or a named phase of one, with a place and an operator: the Stargate sites, Meta's Prometheus and Hyperion, Microsoft's Fairwater sites, AWS Project Rainier, xAI's Colossus, and campuses built by Crusoe, Vantage, Nscale, Nebius and others for AI labs. Chip purchase deals and cloud contracts without a site are left out.

Where do the megawatts come from?

From the operator's own announcement where it gave one, otherwise from the reporting linked on the build. When nobody stated a capacity the column is empty rather than an estimate. Megawatts are the announced campus capacity, usually IT load; a note says when a figure is IT power, a first phase or a target.

How are delays and cancellations tracked?

Every change (capacity, status, target date, tenant, investment) is a dated row with its source, kept forever on the build's page, on the Changes page and at /api/changes. Nothing is overwritten: when Oracle and OpenAI dropped the Abilene expansion, the 1.8 GW row stays in the history next to the 1.2 GW that followed.

How often is it updated?

Every Tuesday at 14:30 UTC. A small agent reads data center RSS feeds and newsrooms (a list it grows itself), SEC filings and news search, for changes to the builds on file and for new ones; anything it finds is marked Unverified until checked by hand.