Skip to content

Stargate Milam County (Freebird)

SB Energy · Milam County, Texas · 1.2 GW · Building

Source

SB Energy builds and runs the 1.2 GW site; phase one, four data halls in 548,950 sq ft, is filed for completion on October 15, 2026.

Facts

As of Apr 22, 2026
Operator
SB Energy
Tenant
OpenAI
Partners
SoftBank
Capacity
1.2 GW
Power
SB Energy powered infrastructure
Location
Milam County, Texas · Cloud regions nearby
Announced
Sep 23, 2025
Target online
Oct 15, 2026
Program
Stargate · The deal on Partnerships

History

Append-only, newest first
DateChange
Apr 22, 2026Target online 2026 to Oct 15, 2026State filing gives phase one a completion date of October 15Source
Sep 23, 2025AnnouncedSource

Related builds

Sources and links

AI data center changes by email

Tuesdays, only in weeks when a build is announced, delayed, expanded, paused or cancelled.

Double opt-in. Unsubscribe any time.