Nscale Ward County campus
Nscale · Barstow, Texas · 240 MW · Building
Nscale is deploying about 104,000 NVIDIA GB300 GPUs for Microsoft at a roughly 240 MW campus in Ward County, Texas, leased from Ionic Digital.
Facts
As of Oct 15, 2025- Capacity
- 240 MWAbout 240 MW campus for Microsoft (financing covers about 200 MW of IT); plan to scale to 1.2 GW
- Chips
- About 104,000 NVIDIA GB300; later Vera Rubin
- Announced
- Oct 15, 2025
- Target online
- Q3 2026Phased from Q3 2026
- Online
- Building
- Announced
- StoppedPaused or cancelled
Related builds
BuildingTarget 202611 GW
Project MatadorFermi America is building a private power and AI data center campus in Carson County near Amarillo, Texas, planned at 11 GW or more.AnnouncedTarget H1 2028Unverified2 GW
Caldwell Valley Technology ParkTract assembled a nearly 3,000 acre campus in Caldwell County, Texas, planned for over 2 GW of data centers from 2028.BuildingTarget 20272 GW
Sweetwater 1 and 2IREN 2 GW grid-connected site at Sweetwater, Texas; the first substation was energized in 2026 and initial AI capacity is planned for 2027.BuildingTarget H2 20261.4 GW
Vantage Frontier campusTen buildings on 1,200 acres, 1.4 GW of GPU capacity, first building due in the second half of 2026. OpenAI named Shackelford County for an Oracle-developed Stargate site a month later.AnnouncedUnverified1.35 GW
Monarch Compute CampusNscale bought the Monarch campus in Mason County, West Virginia, and signed a letter of intent to host up to 1.35 GW of Vera Rubin GPUs for Microsoft.Partly onlineTarget 20301.2 GW
SINES Data Campus (Start Campus)Start Campus is building a 1.2 GW campus at a former coal plant in Sines, where Nscale deploys over 66,000 Nvidia Rubin GPUs for Microsoft.Partly onlineTarget 20261.2 GW
Stargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.BuildingTarget Oct 15, 20261.2 GW
Stargate Milam County (Freebird)SB Energy builds and runs the 1.2 GW site; phase one, four data halls in 548,950 sq ft, is filed for completion on October 15, 2026. | Build | Location | Capacity | Status | Target online |
|---|
Project MatadorFermi America is building a private power and AI data center campus in Carson County near Amarillo, Texas, planned at 11 GW or more.Fermi America · Amarillo, Texas · Building · Target 2026 | Amarillo, Texas | 11 GW | Building | 2026 |
Caldwell Valley Technology ParkTract assembled a nearly 3,000 acre campus in Caldwell County, Texas, planned for over 2 GW of data centers from 2028.Tract · Lockhart, Texas · Announced · Target H1 2028 · unverified | Lockhart, Texas | 2 GW | Announced | H1 2028 |
Sweetwater 1 and 2IREN 2 GW grid-connected site at Sweetwater, Texas; the first substation was energized in 2026 and initial AI capacity is planned for 2027.IREN · Sweetwater, Texas · Building · Target 2027 | Sweetwater, Texas | 2 GW | Building | 2027 |
Vantage Frontier campusTen buildings on 1,200 acres, 1.4 GW of GPU capacity, first building due in the second half of 2026. OpenAI named Shackelford County for an Oracle-developed Stargate site a month later.Vantage Data Centers · Shackelford County, Texas · Building · Target H2 2026 | Shackelford County, Texas | 1.4 GW | Building | H2 2026 |
Monarch Compute CampusNscale bought the Monarch campus in Mason County, West Virginia, and signed a letter of intent to host up to 1.35 GW of Vera Rubin GPUs for Microsoft.Nscale for Microsoft · Point Pleasant, West Virginia · Announced · unverified | Point Pleasant, West Virginia | 1.35 GW | Announced | |
SINES Data Campus (Start Campus)Start Campus is building a 1.2 GW campus at a former coal plant in Sines, where Nscale deploys over 66,000 Nvidia Rubin GPUs for Microsoft.Start Campus for Microsoft · Sines, Portugal · Partly online · Target 2030 | Sines, Portugal | 1.2 GW | Partly online | 2030 |
Stargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.Oracle for OpenAI · Abilene, Texas · Partly online · Target 2026 | Abilene, Texas | 1.2 GW | Partly online3 changes | 2026 |
Stargate Milam County (Freebird)SB Energy builds and runs the 1.2 GW site; phase one, four data halls in 548,950 sq ft, is filed for completion on October 15, 2026.SB Energy for OpenAI · Milam County, Texas · Building · Target Oct 15, 2026 | Milam County, Texas | 1.2 GW | Building1 change | Oct 15, 2026 |
Sources and links