AI data center builds

220 builds · 93 gigawatts

Nvidia

Partner on 25 builds · 19 locations · Registry profile

Partnerships

Builds

Announced1.4 GWMGX, Bpifrance, Mistral AI and Nvidia AI campus, Paris regionA joint venture of MGX, Bpifrance, Mistral AI and Nvidia plans Europe's largest AI campus in the Paris region, scaling to 1.4 GW.Partner, run by MGX · FranceAnnouncedUnverified1.35 GWMonarch Compute CampusNscale bought the Monarch campus in Mason County, West Virginia, and signed a letter of intent to host up to 1.35 GW of Vera Rubin GPUs for Microsoft.Partner, run by Nscale · Point Pleasant, West Virginia · NVIDIA Vera Rubin NVL72Partly onlineTarget 20301.2 GWSINES Data Campus (Start Campus)Start Campus is building a 1.2 GW campus at a former coal plant in Sines, where Nscale deploys over 66,000 Nvidia Rubin GPUs for Microsoft.Partner, run by Start Campus · Sines, Portugal · 12,600+ Nvidia Blackwell Ultra GPUs plus 66,000+ Nvidia Rubin GPUs · $10BPartly onlineTarget 20261.2 GWStargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.Partner, run by Oracle · Abilene, Texas · NVIDIA GB200 · 3 changesBuildingTarget Jun 20271 GWData Center Valley, EkibastuzThe USD 10 billion Data Center Valley in Ekibastuz, Kazakhstan, backed by Nvidia and Firebird, is planned to scale to 1 GW.Partner, run by Firebird · Ekibastuz, Kazakhstan · $10BBuildingTarget 20261 GWStargate UAEThe first 1 GW phase of the 5 GW UAE-US AI Campus, built by G42 with OpenAI, Oracle, Nvidia, Cisco and SoftBank. The UAE is now revising the campus into several sites.Partner, run by G42 · Abu Dhabi, United Arab Emirates · NVIDIA GB300 · $30B · 1 changeAnnounced1 GWZankore by Indosat AI factory platformIndosat, Ooredoo, Nokia and Nvidia launched Zankore, targeting 1 GW of Nvidia AI factory capacity in Indonesia.Partner, run by Indosat Ooredoo Hutchison · Indonesia · NvidiaOnlineTarget 2027946 MWColossus 2Operational from September 3, 2026 at about 946 MW of IT power, by Epoch AI's count the largest AI data center.Partner, run by SpaceXAI · Memphis, Tennessee · NVIDIA B200, B300 · 1 changeAnnouncedUnverified500 MWxAI and HUMAIN data center, Saudi ArabiaHUMAIN and xAI plan a 500 MW data center in Saudi Arabia powered by Nvidia chips.Partner, run by HUMAIN · Saudi Arabia · NvidiaAnnounced360 MWDayOne and Firmus AI campus, Kabil, BatamDayOne and Firmus are developing a 360 MW AI campus in Batam, with access to up to 170,000 Nvidia accelerators.Partner, run by DayOne · Batam, Indonesia · Up to 170,000 Nvidia acceleratorsPartly onlineTarget 2027300 MWFirebird AI factory, ArmeniaFirebird launched an Nvidia AI factory in Armenia and plans 300 MW and more than 70,000 GPUs there by end 2027.Partner, run by Firebird · Armenia · More than 70,000 Nvidia Rubin and Blackwell GPUsPartly online260 MWDenton HPC campusCore Scientific is converting its Denton, Texas, site into a roughly 260 MW GPU data center leased to CoreWeave.Partner, run by Core Scientific · Denton, Texas · NVIDIA GPUsBuildingTarget Q3 2026240 MWNscale Ward County campusNscale is deploying about 104,000 NVIDIA GB300 GPUs for Microsoft at a roughly 240 MW campus in Ward County, Texas, leased from Ionic Digital.Partner, run by Nscale · Barstow, Texas · About 104,000 NVIDIA GB300; later Vera RubinBuildingTarget 2026230 MWNscale Narvik (was Stargate Norway)Built by Nscale for an Nscale and Aker joint venture on hydropower. OpenAI announced it as Stargate Norway, then did not sign; Microsoft took the capacity.Partner, run by Nscale · Narvik, Norway · NVIDIA Rubin (30,000 for Microsoft) · 1 changePartly onlineTarget 2026200 MWChildress Horizon 1-4IREN is building four liquid-cooled halls at Childress, Texas, to host NVIDIA GB300 GPUs for Microsoft under a $9.7 billion contract.Partner, run by IREN · Childress, Texas · NVIDIA GB300 · $5.8BAnnouncedUnverified200 MWEgypt AI data center (Vodafone, Elsewedy, Cassava)Egypt plans a 200 MW, USD 1 billion AI data center with Nvidia technology, starting with a 20 MW phase by Vodafone, Elsewedy and Cassava.Partner, run by Cassava Technologies · Egypt · Nvidia · $1BAnnouncedTarget 2028200 MWNAVER GAK Sejong AI factoryNAVER plans to grow its Nvidia AI factory at GAK Sejong from 55 MW to 200 MW by 2028, with Brookfield financing up to USD 9 billion.Partner, run by NAVER · Sejong, South Korea · Nvidia Vera Rubin and BlackwellAnnounced121 MWTydal Data Center, NorwayBitdeer signed a USD 4.7 billion lease with Volta for 121 MW of IT capacity at its Tydal facility in Norway for a leading AI lab.Partner, run by Bitdeer · Tydal, Norway · Nvidia GPUsAnnounced100 MWFoxconn and Nvidia AI factory, KaohsiungFoxconn and Nvidia plan an AI data center in Taiwan targeted at 100 MW, built in phases with some in Kaohsiung.Partner, run by Foxconn · Kaohsiung, Taiwan · NvidiaBuildingTarget Q1 202790 MWNscale AI Campus, Loughton (Microsoft)Nscale is building a GBP 2 billion AI campus in Loughton with Microsoft as anchor tenant, 50 MW scalable to 90 MW, though grid power is delayed.Partner, run by Nscale · Loughton, United Kingdom · 23,040 Nvidia GB300 GPUs initiallyAnnouncedTarget 202736 MWNexus AI Factory, MoroccoNexus Core Systems signed an MoU to invest MAD 12 billion in a two-phase AI factory in Morocco, starting in Nouaceur.Partner, run by Nexus Core Systems · Nouaceur, Morocco · $1.29BAnnouncedTarget Early 2026Not statedDeutsche Telekom and Nvidia Industrial AI Cloud, MunichDeutsche Telekom and Nvidia set up a EUR 1 billion AI factory in Munich with up to 10,000 Blackwell GPUs for German industry.Partner, run by Deutsche Telekom · Munich, Germany · Up to 10,000 Nvidia Blackwell GPUs · $1.15BOnlineNot statedFairwater AtlantaThe second Fairwater site, linked to Wisconsin over Microsoft's AI WAN so one training job can span both.Partner, run by Microsoft · Atlanta, Georgia · NVIDIA GB200, GB300OnlineTarget 2026Not statedFairwater WisconsinThree buildings on 315 acres run as one supercomputer; fully operational in June 2026, with a second facility under construction next door.Partner, run by Microsoft · Mount Pleasant, Wisconsin · NVIDIA GB200 · $7.3B · 2 changesPausedTarget Q1 2026Not statedStargate UKSovereign compute with Nvidia and Nscale in North East England. OpenAI paused it in April 2026, citing energy costs and regulation.Partner, run by Nscale · Cobalt Park, North Tyneside, United Kingdom · Up to 8,000 NVIDIA GPUs, scaling to 31,000 · 1 change

What changed

Newest first
UpdateSep 10

Stargate UAE

The UAE is revising the 5 GW campus into a network of sites after attacks linked to the US-Iran war; G42 says work is progressing

StatusSep 3

Colossus 2

Building Online

StatusJun 23

Fairwater Wisconsin

Building Online

TenantApr 15

Nscale Narvik (was Stargate Norway)

openai microsoft
OpenAI did not conclude an offtake deal; Microsoft takes the capacity

NscaleCNBC ↗
StatusApr 9

Stargate UK

Announced Paused

NscaleDCD ↗
CapacityMar 6

Stargate Abilene

1.8 GW 1.2 GW
Oracle and OpenAI dropped the expansion to 2 GW

OracleDCD ↗
CapacitySep 23, 2025

Stargate Abilene

1.2 GW 1.8 GW
A potential 600 MW expansion near the site

StatusSep 23, 2025

Stargate Abilene

Building Partly online

InvestmentSep 18, 2025

Fairwater Wisconsin

$3.3B $7.3B
A second facility of similar scale added