Colossus 2

xAI · Memphis, Tennessee · 946 MW · Online

Source

Operational from September 3, 2026 at about 946 MW of IT power, by Epoch AI's count the largest AI data center.

Facts

As of Sep 3, 2026
Operator
xAI
Partners
Nvidia
Capacity
946 MW, IT power, target 1,531 MW in early 2027
Chips
NVIDIA B200, B300
Power
Temporary gas turbines and grid; a 1.2 GW gas plant due mid-2027
Location
Memphis, Tennessee · Cloud regions nearby
Target online
2027

History

Append-only, newest first
DateChange
Sep 3, 2026Building to OnlineSource
Sep 3, 2026AnnouncedSource