Childress Horizon 1-4

IREN · Childress, Texas · 200 MW · Partly online

Source

IREN is building four liquid-cooled halls at Childress, Texas, to host NVIDIA GB300 GPUs for Microsoft under a $9.7 billion contract.

Facts

As of Nov 3, 2025
Operator
IREN
Tenant
Microsoft
Partners
Nvidia, dell
Capacity
200 MW200 MW critical IT across four liquid-cooled Horizon halls on a 750 MW campus
Chips
NVIDIA GB300
Investment
GPU and equipment purchase from Dell of about $5.8B; Microsoft contract about $9.7B over five years $5.8B
Location
Childress, Texas · Cloud regions nearby
Announced
Nov 3, 2025
Target online
20262026 in phases
On file since
Nov 3, 2025 · SEC

Related builds

BuildingTarget 202611 GWProject MatadorFermi America is building a private power and AI data center campus in Carson County near Amarillo, Texas, planned at 11 GW or more.Fermi America · Amarillo, TexasAnnouncedTarget H1 2028Unverified2 GWCaldwell Valley Technology ParkTract assembled a nearly 3,000 acre campus in Caldwell County, Texas, planned for over 2 GW of data centers from 2028.Tract · Lockhart, TexasBuildingTarget 20272 GWSweetwater 1 and 2IREN 2 GW grid-connected site at Sweetwater, Texas; the first substation was energized in 2026 and initial AI capacity is planned for 2027.IREN · Sweetwater, TexasBuildingTarget H2 20261.4 GWVantage Frontier campusTen buildings on 1,200 acres, 1.4 GW of GPU capacity, first building due in the second half of 2026. OpenAI named Shackelford County for an Oracle-developed Stargate site a month later.Vantage Data Centers · Shackelford County, Texas · $25BAnnouncedUnverified1.35 GWMonarch Compute CampusNscale bought the Monarch campus in Mason County, West Virginia, and signed a letter of intent to host up to 1.35 GW of Vera Rubin GPUs for Microsoft.Nscale for Microsoft · Point Pleasant, West Virginia · NVIDIA Vera Rubin NVL72Partly onlineTarget 20301.2 GWSINES Data Campus (Start Campus)Start Campus is building a 1.2 GW campus at a former coal plant in Sines, where Nscale deploys over 66,000 Nvidia Rubin GPUs for Microsoft.Start Campus for Microsoft · Sines, Portugal · 12,600+ Nvidia Blackwell Ultra GPUs plus 66,000+ Nvidia Rubin GPUs · $10BPartly onlineTarget 20261.2 GWStargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.Oracle for OpenAI · Abilene, Texas · NVIDIA GB200 · 3 changesBuildingTarget Oct 15, 20261.2 GWStargate Milam County (Freebird)SB Energy builds and runs the 1.2 GW site; phase one, four data halls in 548,950 sq ft, is filed for completion on October 15, 2026.SB Energy for OpenAI · Milam County, Texas · 1 change