Microsoft and G42 200 MW expansion via Khazna, UAE

Khazna Data Centers · Abu Dhabi, United Arab Emirates · 200 MW · Announced

Source

Microsoft and G42 are adding 200 MW of data center capacity in the UAE through Khazna, starting to come online before end 2026.

Facts

As of Nov 5, 2025
Tenant
Microsoft
Partners
G42
Capacity
200 MW200 MW expansion
Location
Abu Dhabi, United Arab Emirates · Cloud regions nearby
Announced
Nov 5, 2025
Target online
20262026 (start coming online)
On file since
Nov 5, 2025 · news.microsoft.com

Related builds

AnnouncedUnverified1.35 GWMonarch Compute CampusNscale bought the Monarch campus in Mason County, West Virginia, and signed a letter of intent to host up to 1.35 GW of Vera Rubin GPUs for Microsoft.Nscale for Microsoft · Point Pleasant, West Virginia · NVIDIA Vera Rubin NVL72Partly onlineTarget 20301.2 GWSINES Data Campus (Start Campus)Start Campus is building a 1.2 GW campus at a former coal plant in Sines, where Nscale deploys over 66,000 Nvidia Rubin GPUs for Microsoft.Start Campus for Microsoft · Sines, Portugal · 12,600+ Nvidia Blackwell Ultra GPUs plus 66,000+ Nvidia Rubin GPUs · $10BPausedTarget May 20261 GWMicrosoft and G42 geothermal data center, OlkariaKenya suspended the USD 1 billion geothermal-powered data center planned with Microsoft and G42 at Olkaria over power needs.G42 for Microsoft · Naivasha, Kenya · $1BBuildingTarget 20261 GWStargate UAEThe first 1 GW phase of the 5 GW UAE-US AI Campus, built by G42 with OpenAI, Oracle, Nvidia, Cisco and SoftBank. The UAE is now revising the campus into several sites.G42 for OpenAI · Abu Dhabi, United Arab Emirates · NVIDIA GB300 · $30B · 1 changeAnnounced900 MWCrusoe Abilene expansion for MicrosoftMicrosoft leases 900 MW at Crusoe's Abilene campus, the capacity OpenAI and Oracle chose not to take when they stopped at 1.2 GW.Crusoe for Microsoft · Abilene, TexasAnnounced500 MWKhazna and Eni AI campus, Ferrera ErbognoneKhazna and Eni signed terms for a JV to build a 500 MW AI data center campus in Ferrera Erbognone, Lombardy, powered by a gas plant with CO2 capture.Khazna Data Centers · Ferrera Erbognone, ItalyPartly online300 MWNebius VinelandDeveloped by DataOne for Nebius to serve its $17 billion Microsoft deal; New Jersey fined it over $1 million in September 2026 for unpermitted gas generators.Nebius for Microsoft · Vineland, New Jersey · 1 changeBuildingTarget Q3 2026240 MWNscale Ward County campusNscale is deploying about 104,000 NVIDIA GB300 GPUs for Microsoft at a roughly 240 MW campus in Ward County, Texas, leased from Ionic Digital.Nscale for Microsoft · Barstow, Texas · About 104,000 NVIDIA GB300; later Vera Rubin