A $3 billion, 280 MW AI campus near Harwood, North Dakota, with 200 MW leased to an unnamed investment-grade hyperscaler.

Facts

As of Aug 18, 2025
Capacity
280 MW280 MW initial; 200 MW leased to an unnamed investment-grade hyperscaler with right of first refusal on 800 MW more (1 GW potential)
Investment
$3 billion initial campus $3B
Location
Harwood, North Dakota · Cloud regions nearby
Announced
Aug 18, 2025
Target online
20262026 initial, full capacity early 2027
On file since
Aug 18, 2025 · ir.applieddigital.com