Polaris Forge 1

Applied Digital · Ellendale, North Dakota · 400 MW · Partly online

Source

Applied Digital campus in Ellendale, North Dakota, leased to CoreWeave for 400 MW of critical IT load under roughly 15-year leases.

Facts

As of Jun 2, 2025
Tenant
CoreWeave
Capacity
400 MW400 MW critical IT across three CoreWeave leases
Location
Ellendale, North Dakota · Cloud regions nearby
Announced
Jun 2, 2025
Target online
2025
On file since
Jun 2, 2025 · ir.applieddigital.com