Helios
Galaxy Digital · Dickens, Texas · 800 MW · Partly online
Galaxy converted its Helios bitcoin site in Dickens County, Texas, into an AI campus leased to CoreWeave; 133 MW of IT was delivered in Q2 2026.
Facts
As of Mar 28, 2025- Operator
- Galaxy Digital
- Tenant
- CoreWeave
- Capacity
- 800 MW, 800 MW gross approved power, all committed to CoreWeave (526 MW critical IT); campus path to 3.6 GW
- Power
- ERCOT grid; 1.6 GW approved
- Location
- Dickens, Texas · Cloud regions nearby
- Announced
- Mar 28, 2025
- Target online
- Phase I delivered Q2 2026; Phase II Q2 2027
History
Append-only, newest firstRelated builds
| Build | Capacity | |||
|---|---|---|---|---|
| Amarillo, Texas | 11 GW | Building | Initial power targeted 2026 | |
| Lockhart, Texas | 2 GW | Announced | Initial utility delivery first half of 2028 | |
| Sweetwater, Texas | 2 GW | Building | Sweetwater 1 initial phase 2027 | |
| Shackelford County, Texas | 1.4 GW | Building | H2 2026 | |
| Abilene, Texas | 1.2 GW | Partly online3 changes | 2026 | |
| Milam County, Texas | 1.2 GW | Building1 change | Oct 15, 2026 | |
| Childress, Texas | 1 GW | Announced | Construction to begin Q3 2026 | |
| El Paso, Texas | 1 GW | Building1 change |
Sources and links
- Galaxy Q2 2026 overview (8-K Ex 99.2) · SEC · Aug 5, 2026
- Galaxy Q2 2025 results (CoreWeave commits to full 800 MW) · SEC · Aug 5, 2025
Across fru.dev: Galaxy Digital on Companies, cloud regions on Regions.