Galaxy Digital · Dickens, Texas · 800 MW · Partly online

Source

Galaxy converted its Helios bitcoin site in Dickens County, Texas, into an AI campus leased to CoreWeave; 133 MW of IT was delivered in Q2 2026.

Facts

As of Mar 28, 2025
Tenant
CoreWeave
Capacity
800 MW, 800 MW gross approved power, all committed to CoreWeave (526 MW critical IT); campus path to 3.6 GW
Power
ERCOT grid; 1.6 GW approved
Location
Dickens, Texas · Cloud regions nearby
Announced
Mar 28, 2025
Target online
Phase I delivered Q2 2026; Phase II Q2 2027

History

Append-only, newest first
DateChange
Mar 28, 2025AnnouncedSource

Related builds

BuildCapacity
Project MatadorFermi America · Amarillo, Texas · Building11 GW
Caldwell Valley Technology ParkTract · Lockhart, Texas · Announced · unverified2 GW
Sweetwater 1 and 2IREN · Sweetwater, Texas · Building2 GW
Vantage Frontier campusVantage Data Centers · Shackelford County, Texas · Building1.4 GW
Stargate AbileneOracle for OpenAI · Abilene, Texas · Partly online1.2 GW
Stargate Milam County (Freebird)SB Energy for OpenAI · Milam County, Texas · Building1.2 GW
Crusoe Childress campusCrusoe · Childress, Texas · Announced1 GW
Meta El PasoMeta · El Paso, Texas · Building1 GW