CyrusOne DFW7

CyrusOne · Fort Worth, Texas · 200 MW · Building

Source

CyrusOne is building the 200 MW DFW7 campus in Fort Worth, Texas, next to an Eolian battery storage site to reuse its grid connection.

Facts

As of Jan 13, 2026
Operator
CyrusOne
Partners
eolian
Capacity
200 MW200 MW campus
Power
Existing transmission and substation at Eolian Chisholm Grid battery site, ERCOT
Location
Fort Worth, Texas · Cloud regions nearby
Announced
Jan 13, 2026
On file since
Jan 13, 2026 · cyrusone.com

Related builds

BuildingTarget 202611 GWProject MatadorFermi America is building a private power and AI data center campus in Carson County near Amarillo, Texas, planned at 11 GW or more.Fermi America · Amarillo, TexasAnnouncedTarget H1 2028Unverified2 GWCaldwell Valley Technology ParkTract assembled a nearly 3,000 acre campus in Caldwell County, Texas, planned for over 2 GW of data centers from 2028.Tract · Lockhart, TexasBuildingTarget 20272 GWSweetwater 1 and 2IREN 2 GW grid-connected site at Sweetwater, Texas; the first substation was energized in 2026 and initial AI capacity is planned for 2027.IREN · Sweetwater, TexasBuildingTarget H2 20261.4 GWVantage Frontier campusTen buildings on 1,200 acres, 1.4 GW of GPU capacity, first building due in the second half of 2026. OpenAI named Shackelford County for an Oracle-developed Stargate site a month later.Vantage Data Centers · Shackelford County, Texas · $25BPartly onlineTarget 20261.2 GWStargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.Oracle for OpenAI · Abilene, Texas · NVIDIA GB200 · 3 changesBuildingTarget Oct 15, 20261.2 GWStargate Milam County (Freebird)SB Energy builds and runs the 1.2 GW site; phase one, four data halls in 548,950 sq ft, is filed for completion on October 15, 2026.SB Energy for OpenAI · Milam County, Texas · 1 changeAnnouncedTarget Q3 20261 GWCrusoe Childress campusCrusoe and Lancium plan a 1 GW AI data center campus in Childress, Texas, for an unnamed hyperscaler, repeating their Abilene model.Crusoe · Childress, TexasBuilding1 GWMeta El PasoMeta's 29th data center, broken ground in October 2025 as a site that can scale to 1 GW.Meta · El Paso, Texas · $10B · 1 change