Vantage South Wales campuses (Newport CWL1, Bridgend, Bro Tathan)

Vantage Data Centers · Newport, United Kingdom · 1 GW · Partly online

Source

Vantage plans more than 1 GW across Newport, Bridgend and Bro Tathan in the South Wales AI Growth Zone, with Nebius leasing capacity at CWL1.

Facts

As of Sep 25, 2026
Tenant
Nebius
Capacity
1 GWMore than 1 GW AI-ready capacity planned across three sites
Location
Newport, United Kingdom · Cloud regions nearby
On file since
Sep 25, 2026 · w.media

Related builds

BuildingTarget H2 20261.4 GWVantage Frontier campusTen buildings on 1,200 acres, 1.4 GW of GPU capacity, first building due in the second half of 2026. OpenAI named Shackelford County for an Oracle-developed Stargate site a month later.Vantage Data Centers · Shackelford County, Texas · $25BAnnouncedTarget 20291 GWElsham Tech Park, North LincolnshireElsham Tech Park, a 1 GW AI data center campus on the former RAF Elsham Wolds airfield, received outline planning approval in March 2026.Greystoke · Elsham, United KingdomBuildingTarget 20281 GWStargate Wisconsin (Lighthouse)Four data centers with close to a gigawatt of AI capacity, developed by Vantage with Oracle for OpenAI; completion scheduled for 2028.Vantage Data Centers for OpenAI · Port Washington, Wisconsin · $15B · 1 changeAnnouncedTarget 2030300 MWClearstone Ebbsfleet AI Data Center campusClearstone plans a 300 MW AI data center campus near Ebbsfleet, Kent, targeting operation in 2030.Clearstone · Ebbsfleet, United KingdomBuilding300 MWVantage JHB1 campus (ex-Yondr), Sedenak Tech ParkVantage acquired Yondr's 300 MW hyperscale campus in Sedenak Tech Park, Johor, which will host three data centers when complete.Vantage Data Centers · Kulai, MalaysiaBuildingTarget Q2 2026224 MWVantage NV1Vantage is building a 224 MW, four-building AI campus in Storey County outside Reno, Nevada, with the first two buildings leased.Vantage Data Centers · McCarran, Nevada · $3BAnnounced200 MWEarlham Gigagrid offshore data center, North SeaOrcadian Energy began assessing an offshore power station and 200 MW data center on the Earlham gas discovery in the Southern North Sea.Orcadian Energy · United KingdomBuildingTarget Late 2025192 MWVantage OH1Vantage broke ground on a 192 MW hyperscale campus in New Albany, Ohio, its first in the Midwest, investing over $2 billion.Vantage Data Centers · New Albany, Ohio · $2B