AI data center builds

220 builds · 93 gigawatts

Vantage OH1

Vantage Data Centers · New Albany, Ohio · 192 MW · Building

Source

Vantage broke ground on a 192 MW hyperscale campus in New Albany, Ohio, its first in the Midwest, investing over $2 billion.

Facts

As of Oct 25, 2024
Capacity
192 MW
Investment
Over $2B $2B
Location
New Albany, Ohio · Cloud regions nearby
Announced
Oct 25, 2024
Target online
Late 2025First building late 2025
On file since
Oct 25, 2024 · Vantage

Related builds

BuildingTarget H2 20261.4 GWVantage Frontier campusTen buildings on 1,200 acres, 1.4 GW of GPU capacity, first building due in the second half of 2026. OpenAI named Shackelford County for an Oracle-developed Stargate site a month later.Vantage Data Centers · Shackelford County, Texas · $25BBuildingTarget 20261 GWPrometheusMeta's first gigawatt AI supercluster, expected online in 2026.Meta · New Albany, OhioBuildingTarget 20281 GWStargate Wisconsin (Lighthouse)Four data centers with close to a gigawatt of AI capacity, developed by Vantage with Oracle for OpenAI; completion scheduled for 2028.Vantage Data Centers for OpenAI · Port Washington, Wisconsin · $15B · 1 changePartly online1 GWVantage South Wales campuses (Newport CWL1, Bridgend, Bro Tathan)Vantage plans more than 1 GW across Newport, Bridgend and Bro Tathan in the South Wales AI Growth Zone, with Nebius leasing capacity at CWL1.Vantage Data Centers for Nebius · Newport, United KingdomBuilding300 MWVantage JHB1 campus (ex-Yondr), Sedenak Tech ParkVantage acquired Yondr's 300 MW hyperscale campus in Sedenak Tech Park, Johor, which will host three data centers when complete.Vantage Data Centers · Kulai, MalaysiaBuildingTarget Q2 2026224 MWVantage NV1Vantage is building a 224 MW, four-building AI campus in Storey County outside Reno, Nevada, with the first two buildings leased.Vantage Data Centers · McCarran, Nevada · $3BBuildingTarget Late 2027192 MWVantage VA4Vantage is investing $2 billion in a 192 MW, three-building campus in Stafford County near Fredericksburg, Virginia.Vantage Data Centers · Stafford, Virginia · $2BAnnouncedTarget End 2030Not statedAWS Ohio expansion (Fayette County first site)AWS plans $10 billion of new Ohio data center investment through 2030, starting with about $5 billion in Fayette County.AWS · Washington Court House, Ohio · $10B
Sources and links