Oracle cloud region, Malaysia
Oracle · Malaysia · Announced · Unverified
Oracle plans to invest more than USD 6.5 billion to open a public cloud region in Malaysia.
Facts
As of Oct 2, 2024- Capacity
- Not stated by the company
- Investment
- More than USD 6.5 billion $6.5B
- Announced
- Oct 2, 2024
Related builds
Announced1.5 GW
YTL Power and JLand campus, JohorYTL Power and JLand plan a gigawatt-scale data center campus in Johor, estimated at 1.3 GW to 1.5 GW.Partly onlineTarget 20261.2 GW
Stargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.Building1 GW
Stargate Michigan (The Barn)Three 550,000 sq ft buildings developed by Related Digital; funding closed in April 2026 and all buildings were under construction by June.Building300 MW
Vantage JHB1 campus (ex-Yondr), Sedenak Tech ParkVantage acquired Yondr's 300 MW hyperscale campus in Sedenak Tech Park, Johor, which will host three data centers when complete.AnnouncedUnverified280 MW
AirTrunk JHB3 and JHB4, Iskandar PuteriAirTrunk plans two new hyperscale campuses, JHB3 and JHB4, in Iskandar Puteri, Johor, adding 280 MW for MYR 12 billion.Announced150 MWDRDPS AI data center with Alibaba affiliate, MelakaDPS Resources signed an MoU with an Alibaba affiliate to explore an AI data center in Melaka, with a first phase of about 150 MW to 180 MW.BuildingNot stated
Google data center and cloud region, Elmina Business ParkGoogle broke ground on its first Malaysian data center and cloud region at Elmina Business Park, Selangor, a USD 2 billion investment.BuildingTarget 2028Not stated
Project Jupiter (Stargate New Mexico)The Oracle-developed Stargate site near the US-Mexico border. The gas pipeline was refused twice, and in September 2026 Oracle sent a force majeure notice. | Build | Location | Capacity | Status | Target online |
|---|
YTL Power and JLand campus, JohorYTL Power and JLand plan a gigawatt-scale data center campus in Johor, estimated at 1.3 GW to 1.5 GW.YTL Power International · Malaysia · Announced | Malaysia | 1.5 GW | Announced | |
Stargate AbileneThe flagship Stargate campus, built by Crusoe on Lancium's site and run by Oracle for OpenAI: eight buildings, about 1.2 GW.Oracle for OpenAI · Abilene, Texas · Partly online · Target 2026 | Abilene, Texas | 1.2 GW | Partly online3 changes | 2026 |
Stargate Michigan (The Barn)Three 550,000 sq ft buildings developed by Related Digital; funding closed in April 2026 and all buildings were under construction by June.Oracle for OpenAI · Saline Township, Michigan · Building | Saline Township, Michigan | 1 GW | Building1 change | |
Vantage JHB1 campus (ex-Yondr), Sedenak Tech ParkVantage acquired Yondr's 300 MW hyperscale campus in Sedenak Tech Park, Johor, which will host three data centers when complete.Vantage Data Centers · Kulai, Malaysia · Building | Kulai, Malaysia | 300 MW | Building | |
AirTrunk JHB3 and JHB4, Iskandar PuteriAirTrunk plans two new hyperscale campuses, JHB3 and JHB4, in Iskandar Puteri, Johor, adding 280 MW for MYR 12 billion.AirTrunk · Iskandar Puteri, Malaysia · Announced · unverified | Iskandar Puteri, Malaysia | 280 MW | Announced | |
| DRDPS AI data center with Alibaba affiliate, MelakaDPS Resources signed an MoU with an Alibaba affiliate to explore an AI data center in Melaka, with a first phase of about 150 MW to 180 MW.DPS Resources Berhad · Melaka, Malaysia · Announced | Melaka, Malaysia | 150 MW | Announced | |
Google data center and cloud region, Elmina Business ParkGoogle broke ground on its first Malaysian data center and cloud region at Elmina Business Park, Selangor, a USD 2 billion investment.Google · Shah Alam, Malaysia · Building | Shah Alam, Malaysia | Not stated | Building | |
Project Jupiter (Stargate New Mexico)The Oracle-developed Stargate site near the US-Mexico border. The gas pipeline was refused twice, and in September 2026 Oracle sent a force majeure notice.Oracle for OpenAI · Santa Teresa, Doña Ana County, New Mexico · Building · Target 2028 | Santa Teresa, Doña Ana County, New Mexico | Not stated | Building1 change | 2028 |