Project Jupiter (Stargate New Mexico)
Oracle sent a force majeure notice over Project Jupiter; the gas pipeline rights-of-way were refused in March and July
OracleTNW ↗
Stargate UAE
The UAE is revising the 5 GW campus into a network of sites after attacks linked to the US-Iran war; G42 says work is progressing
G42Daily Star ↗
Stargate Wisconsin (Lighthouse)
Announced Building
First steel beams went up that week
Vantage Data CentersDCD ↗