AI data center builds

220 builds · 93 gigawatts

Oracle

Runs 4 builds, partner on 2 builds · 2.2 GW stated · 6 locations · Registry profile

Partnerships

Builds

What changed

Newest first
UpdateSep 24

Project Jupiter (Stargate New Mexico)

Oracle sent a force majeure notice over Project Jupiter; the gas pipeline rights-of-way were refused in March and July

OracleTNW ↗
UpdateSep 10

Stargate UAE

The UAE is revising the 5 GW campus into a network of sites after attacks linked to the US-Iran war; G42 says work is progressing

StatusJun 1

Stargate Michigan (The Barn)

Announced Building

OracleDCD ↗
StatusMar 6

Stargate Wisconsin (Lighthouse)

Announced Building
First steel beams went up that week

Vantage Data CentersDCD ↗
CapacityMar 6

Stargate Abilene

1.8 GW 1.2 GW
Oracle and OpenAI dropped the expansion to 2 GW

OracleDCD ↗
CapacitySep 23, 2025

Stargate Abilene

1.2 GW 1.8 GW
A potential 600 MW expansion near the site

StatusSep 23, 2025

Stargate Abilene

Building Partly online