Project Jupiter (Stargate New Mexico)

Oracle · Santa Teresa, Doña Ana County, New Mexico · Building

Source

The Oracle-developed Stargate site near the US-Mexico border. The gas pipeline was refused twice, and in September 2026 Oracle sent a force majeure notice.

Facts

As of Sep 24, 2026
Operator
Oracle
Tenant
OpenAI
Partners
Bloom Energy
Capacity
Not stated by the company
Power
Bloom Energy fuel cells on natural gas, up to 2.45 GW
Location
Santa Teresa, Doña Ana County, New Mexico · Cloud regions nearby
Announced
Sep 23, 2025
Target online
2028
Program
Stargate · The deal on Partnerships

History

Append-only, newest first
DateChange
Sep 24, 2026Oracle sent a force majeure notice over Project Jupiter; the gas pipeline rights-of-way were refused in March and JulySource
Sep 23, 2025AnnouncedSource