Hut 8 · St. Francisville, Louisiana · 245 MW · Building
Hut 8 campus in West Feliciana Parish, Louisiana, with a 245 MW IT lease to Fluidstack for Anthropic, backstopped by Google.
Facts
As of Dec 17, 2025- Capacity
- 245 MW245 MW IT leased to Fluidstack; 330 MW initial utility capacity; ROFO for up to 1,000 MW more IT
- Power
- Entergy; MISO grid, path to 1.3 GW utility capacity
- Announced
- Dec 17, 2025
- Target online
- Q2 2027Q2 2027 first data hall
- On file since
- Dec 17, 2025 · SEC
- Online
- Building
- Announced
- StoppedPaused or cancelled
Related builds
| Build | Location | Capacity | Status | Target online |
|---|
HyperionMeta's largest campus, phased through 2030; in July 2026 the plan grew to 5 GW and up to $50 billion.Meta · Richland Parish, Louisiana · Building · Target 2030 | Richland Parish, Louisiana | 5 GW | Building2 changes | 2030 |
Beacon PointHut 8 1 GW campus in Nueces County, Texas, fully leased as 704 MW of IT capacity to one unnamed high-investment-grade tenant.Hut 8 · Texas · Building · Target Q1 2027 | Texas | 704 MW | Building | Q1 2027 |
Lake MarinerTeraWulf is converting its Lake Mariner campus in western New York into AI halls leased to Fluidstack, with Google backstopping the leases.TeraWulf for Fluidstack · Barker, New York · Partly online · Target H2 2026 | Barker, New York | 360 MW | Partly online | H2 2026 |
Barber LakeCipher is building an AI data center at Barber Lake near Colorado City, Texas, leased for 10 years to Fluidstack with a Google backstop.Cipher Digital for Fluidstack · Colorado City, Texas · Building · Target Sep 2026 | Colorado City, Texas | 300 MW | Building | Sep 2026 |
AWS northwest Louisiana campusesAmazon plans three data center campuses across Caddo and Bossier parishes and Shreveport, Louisiana, now an $18 billion plan.AWS · Shreveport, Louisiana · Announced | Shreveport, Louisiana | Not stated | Announced | |
Sources and links