CloudHQ plans a USD 4.8 billion, six-building campus in Queretaro with 900 MW planned and the first 200 MW of power secured.
Facts
As of Sep 25, 2025- Operator
- CloudHQ
- Capacity
- 900 MW, 900 MW planned; first 200 MW secured
- Investment
- USD 4.8 billion $4.8B
- Power
- Waterless cooling; private substation
- Location
- Queretaro, Mexico · Cloud regions nearby
- Announced
- Sep 25, 2025
- Target online
- 2027 (substations)
History
Append-only, newest first| Date | Change | |
|---|---|---|
| Sep 25, 2025 | AnnouncedSource | mexicobusiness |
Related builds
| Build | Capacity | |||
|---|---|---|---|---|
| Queretaro, Mexico | 300 MW | Partly online | ||
| Queretaro, Mexico | Not stated | Online | Jan 14, 2025 |
Sources and links
- CloudHQ Invests US$4.8 Billion in Queretaro's Data Center Campus · mexicobusiness · Sep 25, 2025
- CloudHQ secures first 200MW for US$4.8bn data campus in Mexico · bnamericas · Sep 25, 2025