NTT DATA and Neysa AI data center cluster, Hyderabad
NTT DATA · Hyderabad, India · 400 MW · Announced
NTT DATA, Neysa and Telangana signed an MoU for a 400 MW AI data center cluster in Hyderabad worth INR 10,500 crore.
Facts
As of Apr 18, 2025- Capacity
- 400 MW400 MW cluster
- Chips
- 25,000 GPUs
- Investment
- INR 10,500 crore (about USD 1.2 billion) $1.2B
- Announced
- Apr 18, 2025
- On file since
- Apr 18, 2025 · w.media
- Online
- Building
- Announced
- StoppedPaused or cancelled
Related builds
Announced3 GW
AirTrunk data center, Raigad (Pen Growth Centre)Maharashtra gave AirTrunk a letter of intent for land at the Raigad Pen Growth Centre for a 3 GW, INR 2 lakh crore data center project.Announced1.6 GWFHFortune Data Center Park, near HyderabadFortune Hospitality & Infra plans a 1.6 GW hyperscale data center park on 200 acres next to Bharat Future City near Hyderabad.AnnouncedTarget 20301 GW
Digital Connexion 1 GW campus, VisakhapatnamDigital Connexion, the Reliance, Brookfield and Digital Realty JV, plans a USD 11 billion, 1 GW campus on 400 acres near Visakhapatnam.AnnouncedTarget 20281 GW
Google AI hub VisakhapatnamA $15 billion, 1 GW AI hub with AdaniConneX and Airtel; the first phase is expected by mid-2028.AnnouncedUnverified1 GW
TCS HyperVault AI data center campus, HyderabadTCS subsidiary HyperVault secured 264 acres in Hyderabad for an AI data center campus of up to 1 GW, with up to INR 70,000 crore planned.Announced500 MW
Sify 500 MW data centre, VisakhapatnamAndhra Pradesh granted Sify extra land for the second phase of its INR 15,266 crore, 500 MW data center project in Visakhapatnam.Announced168 MW
Reliance AI data center for Meta, JamnagarReliance will build a 168 MW AI data center in Jamnagar that Meta will lease, its first in India.BuildingTarget H2 2026120 MW
Reliance multi-gigawatt AI data centers, JamnagarReliance has begun building multi-gigawatt AI data centers in Jamnagar, with over 120 MW due online in the second half of 2026. | Build | Location | Capacity | Status | Target online |
|---|
AirTrunk data center, Raigad (Pen Growth Centre)Maharashtra gave AirTrunk a letter of intent for land at the Raigad Pen Growth Centre for a 3 GW, INR 2 lakh crore data center project.AirTrunk · Pen, India · Announced | Pen, India | 3 GW | Announced | |
| FHFortune Data Center Park, near HyderabadFortune Hospitality & Infra plans a 1.6 GW hyperscale data center park on 200 acres next to Bharat Future City near Hyderabad.Fortune Hospitality & Infra · Hyderabad, India · Announced | Hyderabad, India | 1.6 GW | Announced | |
Digital Connexion 1 GW campus, VisakhapatnamDigital Connexion, the Reliance, Brookfield and Digital Realty JV, plans a USD 11 billion, 1 GW campus on 400 acres near Visakhapatnam.Digital Connexion · Visakhapatnam, India · Announced · Target 2030 | Visakhapatnam, India | 1 GW | Announced | 2030 |
Google AI hub VisakhapatnamA $15 billion, 1 GW AI hub with AdaniConneX and Airtel; the first phase is expected by mid-2028.Google · Visakhapatnam, India · Announced · Target 2028 | Visakhapatnam, India | 1 GW | Announced | 2028 |
TCS HyperVault AI data center campus, HyderabadTCS subsidiary HyperVault secured 264 acres in Hyderabad for an AI data center campus of up to 1 GW, with up to INR 70,000 crore planned.TCS · Hyderabad, India · Announced · unverified | Hyderabad, India | 1 GW | Announced | |
Sify 500 MW data centre, VisakhapatnamAndhra Pradesh granted Sify extra land for the second phase of its INR 15,266 crore, 500 MW data center project in Visakhapatnam.Sify Infinit Spaces · Visakhapatnam, India · Announced | Visakhapatnam, India | 500 MW | Announced | |
Reliance AI data center for Meta, JamnagarReliance will build a 168 MW AI data center in Jamnagar that Meta will lease, its first in India.Reliance Industries for Meta · Jamnagar, India · Announced | Jamnagar, India | 168 MW | Announced | |
Reliance multi-gigawatt AI data centers, JamnagarReliance has begun building multi-gigawatt AI data centers in Jamnagar, with over 120 MW due online in the second half of 2026.Reliance Industries · Jamnagar, India · Building · Target H2 2026 | Jamnagar, India | 120 MW | Building | H2 2026 |
Sources and links